This is BATSE trigger #7912
Light Curves...
View each of the 4 discriminator channels.
More about trigger 7912...
Location (J2000 degrees)
- Right Ascension: 302.641
- Declination: 8.778
- RMS error for location: 3.48941
Times
The start date: 12/19/99
The Start time: 18:30:21
The Burst trigger time (seconds of day) : 66621.177422
The Burst load time (seconds of day) : 66621.208531
IBDB background
Start time (day,seconds) 11531 61104.934484
End time (day,seconds) 11531 72256.293016
Trigger Specifics
Triggered Detectors:
- Detector 2 exceeded threshold.
- Detector 4 exceeded threshold.
- Detector 6 exceeded threshold.
Burst Processing Comment:
GRB. Double spike, dur. ~1.5 s, starts at ~T-0.18 s, max at ~T+1.1 s. Marginally visible above 300 keV. Crab set at ~T-270 s.
Other data
The full report
contains detailed information, about this burst.
Go to the
data for this burst.