Status Report #7:
July 17th 1991
Satellite status:
After a long slew on July 5th, ROSAT became lost due to earthblock and lack of guide stars. Consequently the satellite went into safe mode as it had been too long without reference stars. Recovery procedures were carried out over the weekend of July 6-7th. On July 8th, the first portion of the modified attitude control software was uplinked although for safety reasons the PSPC high voltage was left off and the filter wheel was left closed. All systems were up and running again on July 9th and observations have been continuing successfully in the long-pointing mode ever since. The uploading of new software at this point enabled different pointing constraints to come into play, which allow scheduling of some southern hemisphere targets. GSOC is now using +/- 12 degrees for their sun window, still requiring guide stars for contact orbits.
There follows the newest section of timeline:
16 Jul - 17 Jul UK EX HYDRAE Hellier
17 Jul - 18 Jul WG A3558 Zamorani
18 Jul - 19 Jul US WP23 David
19 Jul - 20 Jul US PG1346+82 Lamb
20 Jul - 21 Jul US Q1413+1143 Turnshek
21 Jul - 22 Jul US 3C294 McCarthy
22 Jul - 23 Jul WG LHS2924 Schmitt
23 Jul - 24 Jul US GC1556+335 Meyer
24 Jul - 25 Jul WG M 31 Truemper
25 Jul - 26 Jul WG M 31 Truemper
26 Jul - 27 Jul WG M 31 Truemper
27 Jul - 28 Jul WG M 31 Truemper
28 Jul - 29 Jul WG NGC 383 Boehringer
29 Jul - 30 Jul US M 33 Long
30 Jul - 31 Jul UK MBM 7 Harris
31 Jul - 1 Aug WG MBM 12 Snowden
1 Aug - 2 Aug US TT ARIETIS Cordova
2 Aug - 3 Aug WG NEP WG
3 Aug - 12 Aug WG Survey Finish WG
13 Aug - 14 Aug US NGC1332 Canizares
14 Aug - 15 Aug UK EXO033319-2554.2 King
15 Aug - 16 Aug US N1399 Jones
16 Aug - 17 Aug WG TYCHO Brinkmann
17 Aug - 18 Aug UK HT CAS Naylor
18 Aug - 19 Aug WG ALP PER Schmitt
19 Aug - 20 Aug US NGC891 Bregman
20 Aug - 21 Aug US PERSEUS-NORTH Kowalski
21 Aug - 22 Aug US PERSEUS-SOUTH Kowalski
22 Aug - 23 Aug US V410TAU Strom
23 Aug - 24 Aug US PLEIADES-CENTER Caillault
24 Aug - 25 Aug US PLEIADES-FIELD Rosner
25 Aug - 26 Aug US V471TAU Shipman
26 Aug - 27 Aug US H0323+022 Madejski
A SASS data processing report will follow in a few days.
Status Report #8
Status Report #6
Select another report
Return to the ROSAT GOF
Curator:
HEASARC Guest Observer Facility
Please use the Feedback link if you have questions on ROSAT.