The European Space Agency's X-ray observatory EXOSAT was operational
from May 1983 to April 1986 and, during that interval, it made 1780 detailed
observations of a wide variety of objects including active galactic nuclei,
stellar coronae, cataclysmic variables, white dwarfs, X-ray binaries, clusters
of Galaxies, and supernova remnants. Between 1983 October and 1987 September,
eighteen volumes of the EXOSAT Express were published. This journal was
used to rapidly disseminate information about the mission status, calibrations,
analysis techniques and other useful information. It was published by the
EXOSAT Observatory team, under the editorial leadership of Dave Andrews
(1983-1986) and Nick White (1986-1987). The Express represents an important
source of knowledge about the mission that has not been published elsewhere.
As the years have gone by, many people have lost copies, or do not have
access to them. At the HEASARC, we receive regular requests for particular
volumes, or articles. To ensure this critical information about the EXOSAT
mission is widely available and does not get lost, we have compiled all
the useful articles and reprinted them here in two parts called "The
Best of the EXOSAT Express." The first part begins with all the "status
reports", written by Dave Andrews, which summarize the key events
and happenings on the mission. These provide an historical overview of
all the key events that occurred during the mission. These are followed
by all the Express articles that dealt with any aspect of the spacecraft
operation, calibration, or analysis techniques.
At the HEASARC, the EXOSAT database is available for online access (please
contact HEASARC Feedback for further details).
The database contains summary data products for each observation, plus
catalogs of detected sources and an observation log. The HEASARC is currently
converting these data products to FITS format. The HEASARC has also recently
obtained a complete copy of the Final Observation Tapes, FOTs, from ESAs
Space Information System, ESIS. These raw data will, before the end of
1993, be made available through the HEASARCs anonymous FTP account. Over
the coming years, the HEASARC plans to convert these data to FITS format.
Articles about these activities will be published in the HEASARCs Legacy
journal (which was based upon the EXOSAT Express model). The following
EXOSAT calibration articles have appeared in Legacy as follows:
EXOSAT was launched on May 26th. Switch-on of the instruments and initial
checkout was completed by June 18th. Instrument calibration and performance
verification was largely completed by August 15th. The observing programme
proper, i.e. the undertaking of observations selected by the COPS (Committee
for Observation Proposal Selection) from the response to AO1 issued in
the summer of 1981, was then started.
EXOSAT, ESA's first X-ray astronomy satellite, though conceived as early
as 1969 and selected in 1973, is intended to make a major contribution
in furthering this branch of astronomy following, as it does, the pioneering
missions of the early '70s and the operation of the Einstein Observatory.
In order to do this within various boundary conditions, such as a mass
limit on the satellite of 500 kg, the spacecraft and scientific instruments
are highly sophisticated and employ advanced technologies, many of them
representing the ultimate in the 'state of the art'. Perhaps then it was
not entirely inconceivable that there would be some teething problems in
the early operational phase, despite the thorough ground testing and calibration
of spacecraft and instruments. It is now possible to put these problems
into perspective, and hopefully lay to rest some of the rumours and speculation
that abounded during the early orbit phase.
Difficulties were experienced with operation of the attitude control
system but refined operational procedures have led to a marked reduction
in the anomalous behaviour. It is estimated that up to 0.75 kg of control
gas out of 14 kg total was wasted through this behaviour. However, assuming
that operations continue as of now, there should be no shortage of attitude
control gas before orbit decay and satellite re-entry. Targets are acquired
to typically 1 arcmin without trimming, and pointing is maintained to within
a few arc sec.
Of the two position sensitive proportional counters (one to each telescope),
one exhibited anomalous behaviour on initial switch-on and has not yet
been reactivated. No clue has emerged as to why this occurred. The second
was operated for a considerable period before it too started to behave
anomalously. Analysis of the data has indicated a gradual build-up of low
energy pulses in the detector. It is possible that the rate of this build-up
can be reduced by operating at lower high voltage settings, hence lower
gas gain. Reactivation and investigation of this detector at new settings
is now planned for early October .
Implementation of optimum settings and operational procedures now ensure
fully satisfactory operation of sixteen proportional counters of the medium
energy experiment, the two channel multiplier arrays of the imaging telescopes
and the gas scintillation spectrometer.
Because of a partial jamming of the mechanism that erects the transmission
grating on telescope number 1, only the grating on telescope number 2 is
now being used.
Performance and Operations
Tables 1 and 2 give the current performance parameters of the EXOSAT
instruments. A major surprise from the early orbit phase was the much lower
than predicted non X-ray background in the medium energy detectors and
the gas scintillator. Indeed the background rates for these detectors in
EXOSAT's high 200.000 km apogee orbit is comparable with those for a low
earth orbit. Thus the main apparent disadvantage of the high orbit has
disappeared while the telemetry rate of 8 kbps, given the flexibility of
the on-board computer, is not a very limiting factor.
The advantages of the high orbit are then immediately apparent. EXOSAT
can be operated in real time continuously for about 80 hours per orbit
without earth obscuration of the celestial target. This means for example
that the light curves of binaries can be followed uninterrupted for many
cycles. It also means that real time decisions to change experiment mode,
insert different filters or the grating can be taken on the basis of data
received as the observation proceeds.
The flexibility of the EXOSAT system (both satellite and ground observatory)
has been fully exercised to cope with changes to the hardware status and
has been well demonstrated by the fact that of the observations to be conducted
on AO1 approved proposals, some 60% are correlated with either ground-based
telescopes and/or the space observatories IUE and IRAS. The flexibility
has also been demonstrated in undertaking observations of targets of opportunity
such as Supernova Evans.
During the calibration and performance verification phases, 60 targets
were observed. Since the AO1 programme was implemented 104 targets have
been observed and of the 199 proposals accepted from AOl (many with several
targets) 66 have been completed or partially completed.
On-board Software
Considerable modifications to the on-board computer (OBC) software,
both system and application programs, have been implemented immediately
prior to and post launch, in response to ground calibration measurements,
early orbit instrument performance, X-ray background variability and
errors in the original software. All changes propagate through the entire
observatory ground system as minor or major modifications to telemetry
handling, real-time data display, data filing and archiving, off- line
analysis, final observation tape (FOT) production, and of course, documentation
The following payload data processing programs (application programs) have
been modified:
GSPC Energy Histograms (GHEBL4):
Compression of 256 channel histograms to 128, 64, 32 or 16 channels. Impression
of burst length filters.
GSPC Direct Mode (GDIR):
New program to accumulate per photon, energy channel and time of arrival
to an accuracy of the sampling selected.
ME Energy Resolution (MHER4)
Background and source energy histograms using detector ID word, and for
the half experiment mode, channel compression and selection.
ME Pulsar Mode (MPULS2):
Background and source histograms as a function of phase.
LE Direct Mode (LDIR1/LDIR2).
Addition of 'diamond-shaped' position filter. Selection of data on valid
position or energy. Removal of rise time data to give an energy/position
mode (telemetry saving).
LE Background monitoring:
New definition: flare mode deleted because background variability precluded
a sensible algorithm definition.
Further changes to LE/ME application programs are in progress and will
be reported in the next issue(s) of the EXPRESS.
Observation Output
A major task has been the determination of the calibration of the many
detectors to produce data available for issue with the observational data
on the Final Observation Tapes (FOT). As of the beginning of October 600
FOTs were required from the calibration and performance verification phases.
Of these 550 have been produced and 453 despatched to the so-called hardware
institutes. FOT production for the AO1 targets has just begun. Clearly
we have a back-log on AO1 of something in excess of seven weeks at this
moment, but strenuous efforts are being and will continue to be made to
bring the issue of the FOTs and the automatic scientific analysis output
back to the planned four weeks after observation.
Real time output from the EX2 graphics system is available to the observer
as the observation proceeds and allows decisions to be taken in the light
of this 'quick look' data on the experiment configuration/OBC modes eg.
filter use, time resolution etc. Hard copy of images and histograms together
with tables in raw data form can be provided, but there is no general facility
available at the Observatory for more detailed scientific analysis of the
quick look data, which has therefore to await the FOT and automatic analysis
output.
Future Plans
Following the problems encountered with the PSDs, 50 proposals, in which
the PSD played a prime role (of the 199 from AO1) were deferred pending
the resolution of the problems. Should the PSDs prove operable but at lower
performance and perhaps with limited lifetime, the COPS will be invited
to group these proposals in order of scientific priority and they will
be time-lined accordingly. Should the proposals be ranked with low priority
or should the PSDs remain inoperable, then those still deferred proposals
should be resubmitted in response to AO2. As things presently stand, responses
to AO2 must assume the worst, i.e. PSDs inoperative, but indicate how the
proposed scientific investigation would be enhanced should they be available.
It is presently anticipated that the AO1 accepted observation proposals
(less the 50 PSD prime proposals) will require until approx. February 1984
to complete. In this case AO2 will be issued in late October or early November
with a six week response time. The AO2 will not be released earlier since
work is still going on updating the Observers Handbook etc., in the light
of the actual performance in orbit.
Some criticism has been received on the short-notice observers have
been given regarding the time-lining of their observation. Rest assured
that we want to give the principal investigators (only) as much notice
as possible. However, with the rather dynamic situation that has prevailed
with regard to the satellite's hardware, in particular the grating mechanism
jamming in late September, time-lining has had to be equally dynamic. We
would rather not issue a time-line unless we have good confidence that
we can stick to it.
Volume 2: OBSERVATORY STATUS AS OF 31ST DECEMBER
1983
EXOSAT was launched on May 26th. Switch-on of the instruments, initial
checkout, instrument calibration and performance verification was largely
completed by August 15th. The observing programme proper, i.e. the undertaking
of observations selected by the COPS (Committee for Observation Proposal
Selection) from the response to AO1 issued in the summer of 1981, was started
on August 16th and is now about two-thirds complete.
Hardware
Operational procedures, implemented as solutions to some of the early
orbit problems experienced with the attitude control system, have virtually
eliminated the anomalous AOCS behaviour previously reported. Two persistent
problems remain however, but these have practically no impact on the operations.
First, jumps in the S and Z gyro drift biases occur from time to time (always
close to perigee) and result, in the case of the Z-gyro, in a spacecraft
attitude drift requiring subsequent correction. There is, at present, no
explanation for the phenomenon. Secondly, on board computer (OBC) memory
parity interrupt errors occur regularly, with definite evidence of increased
frequency as a function of time, and appear to be associated with the parity
bits (no corrupted data, OBC continues to operate) of memory words physically
located on the outside of the memory planes, suggesting an electromagnetic
interference cause. A solution to increased frequency, should this become
unacceptable, is to refresh (write to memory) from time to time the affected
memory locations, presently done only when updated system software is loaded.
Analysis of flight data and ground tests of the flight spare model of
the position sensitive detector (PSD) have suggested that the anomalous
behaviour of PSD1 could be explained in terms of a gradual build up of
a deposit on an internal electrode, eventually producing a discharge characteristic
of a single electron spectrum. In orbit evacuated bake-out of PSD1, using
the gas system solenoid valves to raise the temperature from typically
25 to 50 degrees C, followed by gas filling and venting have resulted in
a successful reactivation of this detector at the minimum anode high voltage
(2307V). This detector is now being used for specific observations as selected
by COPS.
Regrettably, a failure occurred on 28/10 in the operation of the channel
multiplier array of the second imaging telescope such that, typically,
20s after switch on at the minimum high voltage, an exponential decay of
the voltage applied to the rear of the second channel plate and the resistive
disc anode occurs on a time scale of approximately 20s and with a magnitude
of 150V During the short period at nominal voltage, no event data are generated
by the detector. Neither this failure nor the anomalous behaviour of PSD2,
with no successful reactivation following a similar procedure of bake-out
and flushing as for PSD1, are understood. Additional analysis and ground
tests on the flight spares are planned but there will be no operation of
telescope number 2 until further notice. Unfortunately, with the partial
jamming of a mechanism of telescope number 1, this also implies no observations
using the transmission gratings of either telescope.
Operational procedures continue to ensure fully satisfactory performance
of the sixteen proportional counters of the medium energy experiment, the
channel multiplier array of telescope number 1 and the gas scintillation
spectrometer.
Performance and Operations
Tables 1 and 2 give the current performance parameters of the EXOSAT
instruments, including very preliminary figures for the position sensitive
detector of telescope number 1. PSD1 figures are based upon two half hour
background observations, and one three hour AO-1 observation (HT Cas).
It is likely that the lifetime of PSD1 will prove a strong function
of detector gain, given the explanation of gradual internal deposition
and discharge, and its use will be strictly limited to those proposals
approved by the Committee on Observation Proposal Selection (COPS) as relevant
PSD targets. There can be no question of treating the PSD as a general
observatory facility in the sense of a real time decision to use it based
upon a current CMA observation. At its meeting on 21.10.83, the COPS re-scheduled
the 47 deferred AO-1 proposals within 3 categories:
- 20 in two priority lists using PSD1/(CMA2)
- 23 using CMA1/(CMA2)
- 4 referred back to proposers for AO-2
Proposals in the PSD1/(CMA2) category are now being scheduled and it
is expected that AO-1 will be substantially complete by the end of March
1984.
Targets of opportunity and co-ordinated observations continue to play
a demanding role on the scheduling and flexibility of the observatory system.
Since the beginning of AO-1, 16 TOO's (including eg. two IRAS Sources)
have been scheduled and of the 340 distinct observations, some 108 were
co-ordinated. Of the 199 proposals accepted from AO-1, 150 have been completed
or are partially complete.
On-board Software
Considerable modifications to the on-board computer (OBC) software,
both system and application programs, have been implemented immediately
prior to and post launch, in response to ground calibration measurements,
early orbit instrument performance and X-ray background variability. All
changes propagate through the entire observatory ground system as minor
or major modifications to telemetry handling, real-time data display, data
filing and archiving, off-line analysis, final observation tape (FOT) production,
and of course, documentation.
Modifications to the payload data processing programs (application programs)
and new programs are briefly described below. Full information is to be
found in Part III of the Observatory User's Guide.
GSPC Energy Histogram (GHEBL4)
A program to accumulate a 256 channel energy histogram from the GSPC
data which has been modified to support the options of energy channel compression
by factors of 2, 4, 8 and 16, and selection of events within specified
burst length (rise time) limits. Accumulation time, channel compression
factor and burst length filtering are all selectable from ground and enable
a trade-off between histogram transmission rate and channel resolution
to be made.
GSPC Direct Mode
A new application program which accumulates the energy of each photon
detected (limited by sample rate) and its arrival time, determined relative
to the previous event by counting the number of samples with zero data.
Hence, an accurate relative arrival time per photon can be established
from a knowledge of sample rate and synchronisation, typically ± 244
µs is for a sample rate of 2048 Hz. This mode, operated with the optimum
burst length (rise time) on-board limits on event selection giving approximately
25/30 events s-1, imposes virtually zero dead time on X-ray data collection
for reasonable telemetry allocations.
ME Energy Histogram (MHER4)
A new application program which accumulates the photon energy for each
photon detected (sample rate limitation) and forms intensity profiles and
256 channel energy histograms with a number of options:
- histogram and intensity profile per Ar/Xe detector, per quadrant of
detectors or per half experiment.
- channel compression of each histogram to 64, 32 or 8 channels.
- selection of a limited number (32,64,128 or 256) of channels of each
histogram to be transmitted.
Options b. and c. can be applied only in the half experiment histogram
configuration eg. detectors ABCD offset to monitor background and detectors
EFGH co-aligned on the source, and in this case the trade-off between resolution,
number of channels and frequency of transmission can be made.
ME Energy Histogram (MHER5)
A new application program, similar to MHER5, but applicable only to
the half experiment configuration of 4 detectors on-source and 4 detectors
off-source, with the following features:
- Energy histogram accumulations per half experiment for 64 selected
channels in Argon and Xenon, normally channels 4-67 (2-20 keV) in Argon
and channels 132-195 (10-30 keV) in Xenon.
- Compression of the 64 channel Ar and Xe histograms per half experiment
to 64, 32 or 8 channels
- Selection of histogram accumulation times and the length of the time
bins in the intensity profile.
As of 31.12.83, coding and testing of this program is complete, but
support facilities such as real time graphics, operations procedures and
filing of the data on the FOT are expected to be finalized during January.
ME Pulsar Mode (MPULS2)
This application program, which accumulates energy histograms as a function
of phase of a known periodic source together with the intensity profile
of the source, is a modified version of an existing program in order to
provide simultaneous background data collection in the half experiment
on-source, half experiment off- source mode. The period T is divided into
129 equal time bins (a correction is applied to the 129th bin to synchronize
the period phase). An energy histogram is accumulated over several periods
for each of the 129 phase bins and the intensity profile is determined
over the same period.
LE Direct Modes- (LDIR1, LDIR2)*
The original LE Direct Mode program has been modified and split into
two quite separate programs (LDIR1, LDIR2) which provide the following
functions:
LDIR1
selection of events with valid energy/time tag
optional background filtering by selection of events having a position
within a square or diamond shaped area of the total FOV
telemetry of energy/time tag data per event
LDIR2
selection of events with valid position
optional background filtering as above
telemetry of position/position + energy/position + energy + rise time
+ time tag per event
*(Those programs are available also for LE2)
LE Background Monitoring (LBGMON)
A continuous monitor of the LE1 and/or LE2 qualified event rate with
a maximum resolution of 32 s-1. Each qualified event sample is buffered
in the OBC memory, summed to the required resolution and telemetered. Any
resolution from 32s-1 in multiples of 32 ms can be selected.
PSD1 'LEP' Monitor (LHER3)
'LEP' or 'low energy pulses' are one manifestation of the anomalous
behaviour of PSD1, explained in terms of a gradual build-up of internal
discharge from an electrode producing a single electron type of exponential
spectrum. Careful monitoring of the magnitude as a function of time is
provided by a program which selects data with a valid energy and zero position
data. An energy histogram is accumulated, providing a direct measure of
the LEP as total counts in energy channels 2-4, and at the same time a
continuous measure of detector gain from the 6 keV internal Fe55 calibration
source radiation.
Observation Output
Calibration data based upon flight performance characteristics is substantially
complete for the LE1 (CMA) and GSPC experiments, whereas for the ME experiment
updated energy channel conversion figures and resolution functions applicable
to the optimized in-orbit detector gain operation will be available shortly.
Production of final observation tapes (FOT's) is now routine for all
experiments and the goal of tape despatch within 28 days of the observation
has almost been reached, with a current period of 20 days between the observation
and tape available at ESOC. Clearing of the accumulated backlog of FOT's
mainly LE1+ LE2 where correction of errors in the linearisation and temperature
compensation algorithms required considerable effort, has been achieved
during November and December, and it is not expected that any additional
delays will accumulate. The observer's copy of the FOT (three are produced:
a master tape, the observer's copy and a second copy, eventually recycled,
required for the automatic analysis) is despatched from ESOC as soon as
possible after production. Visitors to the observatory are encouraged to
hand carry tapes back to their institutes and our data assistants, given
sufficient notice, will prepare for transport any available tapes together
with customs documentation etc. As of 31.12.83, ME, LE1 and GSPC FOT's
have been produced up to day 346, and all LE2 tapes up to the CMA2 failure.
Automatic scientific analysis, carried out on the second copy of the
FOT, started on a routine basis for the LE and GSPC on 28.11.83 and the
output is despatched to observers after verification of scientific integrity.
Current production is at day 260. ME automatic analysis is suspended, while
software modifications are incorporated to reflect changes in the energy
channel conversion and the resolution functions.
Real time output from the EX2 graphics system is available to the observer
as the observation proceeds and allows decisions to be taken in the light
of this 'quick look' data on the experiment configuration/OBC modes eg.
filter use, time resolution etc. Hard copy of images and histograms together
with tables in raw data form can be provided, but there is no general facility
available at the Observatory for more detailed scientific analysis of the
quick look data, which has therefore to await the FOT and automatic analysis
output.
A package of documentation has been sent to all AO-1 observers to aid
FOT analysis and auto output interpretation, comprising updates of relevant
chapters of the FOT handbook (LE/GSPC calibration data, OBC mode description
and FOT record layout) and notes on the LE/GSPC automatic analysis. Equivalent
ME documentation will be sent within about 4 weeks and the formal update
of the FOT handbook should be available by the end of January.
Future Plans
Month-in-advance time lines have until the present remained a somewhat
elusive goal but the observing schedule (as of 31.12.83) was available
until 31.1.84 and we expect February '84 and March '84 to be time-lined
by January 9th and 31st respectively.
Efforts required to schedule co-ordinated observations, the insertion
of targets of opportunity, the response to hardware malfunctions eg. the
grating, the insertion of PSD observations and the handling of last minute
co-ordinate changes all continue to mitigate against an early time-line.
However we will strive to maintain a minimum of four weeks in advance and
to give as much notice as possible to observers. Given four weeks notice,
it is expected that liaison with the relevant duty scientist to confirm
and refine OBC and payload configurations, filter strategy etc should lead
to a time line considered frozen some two weeks prior to the observation.
Documentation for AO-2 is in the final stage of preparation and AO-2
should be released in January 1984. The continuing on-board dynamic situation
and the later than planned availability of certain performance figures
have led to a delay in the issue of the AO.
Volume 3: OBSERVATORY STATUS AS OF 29th FEBRUARY
1984
EXOSAT has been operational for just over 9 months and the programme
of observations approved by the Committee on Observation Proposal Selection
(COPS) in response to AO-1 is about 80% complete (see p. 11-21).
1. Hardware
1.1 Spacecraft
Z- and X-gyro drifts have been increasing monotonically for some months
and are now at 0.60/hr and 0.40/hr respectively, such that the accuracy
of the drift compensation applied by the attitude and orbit control electronics
(AOCE) is reduced. A drift of lower magnitude is observed with the Y-gyro.
Two of the four IRAS gyros (similar design) showed a high drift rate (>0.5°/hr)
after one year in orbit, although 12 such gyros have been in continuous
ground operation for 9 years and only one is presently outside the specification
limit. If the drift rates continue to increase, there will be a gradual
degradation in open-loop performance i.e. during manoeuvres or perigee passes
(<50.000 km) when no update from the star tracker of the inertial reference
is supplied to the gyros, resulting in larger pointing offsets after manoeuvres
or on re-acquisition following perigee and, for observation periods (closed
loop), a longer settling time for stable pointing. Note that, at present,
stable pointing (<5 arcsec) is achieved within approximately 20 mins.
of the 'closed loop' configuration and that the ±1 arcsec limit-cycling
maintains inertial pointing to within ± 3 arcsec in Y and Z with a bias
offset of +5 arcsec in Y (introduced to compensate for an AOCE operational
anomaly). No increase is expected in fuel consumption as a result of increasing
gyro drift rate.
On board computer (OBC) memory parity error interrupts and erroneous
CPU overload errors continue to occur with little impact on operations.
The frequency of memory parity interrupts has reduced from 1 or 2/day to
1/several days, apparently after refreshing (write to memory) the entire
memory area and re-loading a new version of the in-flight software although
the observed gradual reduction is not consistent with the expected behaviour.
There is no explanation for the CPU overload errors which occur about
once per 4 to 6 weeks; diagnostic software has been incorporated to aid
further investigation.
1.2 Payload
1.2.1 LE1
PSD1 is used routinely (Section 2) for those AO-1 observations approved
as relevant PSD targets by the COPS at their meeting on 21.10.83 (Issue
2 p.4). For background limited observations the PSD (operated at its lowest
gas gain) is about a factor of 2 less sensitive than the CMA for source
detection (details in part 1 of the Observers Guide issued as part of AO-2).
To avoid instabilities in the CMA1 detector/HT supply combination at
elevated temperatures, operational procedures have been instituted to maintain
a low average detector temperature consistent with carrying out all observations.
These procedures include:
- 28V power supply (analogue electronics + HT convertors) switch off
for manoeuvres/perigee passes.
angle 'preference' 130° <=
<= 90°
- Observations (particularly co-ordinated) with
angle > 130 or
< 90 degrees (but consistent with other constraints) are scheduled and
interleaved with 'preferred'
angle targets.
There is no operation at present of the grating because of the partial
jamming of the mechanism.
1.2.2 LE2
Reactivation of the detectors of telescope no. 2 has been attempted
from time to time since the malfunctions on 28.10.83 and 11.6.83 respectively
of the CMA and PSD. No explanation exists for either failure. For the CMA,
ideas of temperature effects and mechanical contact problems have been
discussed and the general strategy has been to maintain a cool detector
(approx. 13°C) and to exchange CMA/PSD a few times prior to any test. In
the case of the PSD, which exhibited anomalous behaviour 10 mins. after
the first switch-on, gas flushing and in-orbit 'bake out' (temperature
rise from typically 25°C to 50°C) using the gas system solenoid valves
have so far proved unsuccessful.
After one abortive test on 29.12.83, a second test following the same
procedure on 9.2.84 led to a 'partial reactivation' of CMA2. The detector
was operated at its' minimum HT setting of 900V on plate 1 and 2830V on
plate 2 for approximately 24 hours. Observations were carried out on 0851+202,
OI 417, 4C55.16 (FWHM of LSF for 0851 approx. 25 arcsec) on days 40/41.
Activation of CMA2 at its' nominal gain (1150V on plate 1 and 2910V on
plate 2) resulted in only 30 minutes of normal operation before the malfunction
reappeared. Since then no further operation of CMA2 has been achieved,
although some confidence now exists that the detector has not suffered
an irreversible failure and attempts to re-activate it will be continued.
1.2.3 ME
All sixteen proportional counters operate satisfactorily.
A component failure on 26.11.83 in the drive mechanism electronics for
detectors E,F,G,H (lower half-experiment) such that the motor disable pulse
is not automatically issued after the requisite movement, has led to a
re-appraisal of the simultaneous background monitoring strategy involving
no offset of these detectors. If necessary, a procedure can be established
to use the OBC time-tagged co-and facility to issue the motor disable command
after n seconds of movement. Further information will be given in a forthcoming
issue of the Express.
1.2.4 GSPC
The GSPC continues to operate satisfactorily.
From approximately day 360, gain variations (up to 10%) of the GSPC photomultiplier
have been observed. These are caused by the systematic 28V line switch-off
during maneouvres instituted to maintain CMA1 as cool as possible. The
gain will be measured according to the equivalent energy of light emitting
diode (LED) test pulses and the CCF updated per observation. PI's with
GS prime observations between day 360 and the establishment of the gain
monitoring procedure will be informed separately of the estimated variation.
2. Performance and Operations
Tables 1 and 2 give the current performance parameters of the EXOSAT
instruments based upon the latest analyses of PV/Cal phase data. Note refinements
in the total effective area of the ME, the total effective geometric area
of the GSPC and updated figures for PSD1.
PSD1 operations since re-activation total approximately
24 hours. Preliminary analysis of the data suggests that the 'LEP' (low
energy pulse) behaviour differs somewhat from that observed prior to the
original breakdown on 27.6.83. Initial switch-on 'LEP' count rates are
reproducible at approximately 2 c/s, i.e. no increasing trend from one observation
to the next, followed by relatively stable operation for 1 to 4 hours,
depending apparently on 'age' of gas/whether detector 'baked-out' or not,
and then a steady increase to 4/5 c/s over 1/2 hours with fluctuations
superimposed. An arbitrary maximum allowable LEP of 5 c/s (below the level
observed immediately prior to the breakdown on 27.6.83) has been imposed,
such that PSD observations are practically limited to 300 min. at least
until the phenomenon is better understood. Detector gain variations are
observed consistent with the absence of automatic gain control (AGC) HT
compensation for gas density fluctuations as the detector is 'topped up'
for window leakage. Further details of the PSD performance will be supplied
in the FOT handbook or in forthcoming issues of the EXPRESS.
During the period 1.1.84 to 29.2.84, one sun safety mode trigger on
8/1 and a giant solar 'proton' event on 16/2 disrupted normal operations.
Triggering of the sun safety mode was caused by an operational error in
the initiation of a fairly uncommon Y-axis only slew, and resulted in the
loss of one observation. At 09.07z on 16/2 EXOSAT 'detected' the onset
of a solar proton 'event' which reached a maximum particle density of 660
p cm-2 a-1 sr-1 at satellite altitudes about one hour later, followed
by an exponential decay over 24 hours and a continuing enhanced (approx.
factor 2 higher background in GSPC/ME) activity for about 6 days. Considerable
disruption to the planned observation time line between 16/2 and 22/2 occurred,
particularly with respect to ME/GSPC operations (ref. AO-1 list p.21).
On 28.2.84, snow on the VILSPA antenna caused a telemetry loss for approximately
three hours, (ref. p.44).
AO-1 completion is expected between the middle and end of April, slightly
dependent upon re-scheduling of omitted or disrupted observations. Note
that a number of A0-1 observations, approximately 55, cannot be performed
during the formal AO-1 phase because of coordinated observations after
April or violation of the solar constraint, and will be inserted in the
appropriate place in the AO-2 time line.
3. On-board Software
A new version of the basic in-flight (BIF) software has been loaded
and is running satisfactorily. BIF24 incorporates the following modifications:
- Application program slots: 5 large, 1 small
- Program ROLLER core resident/program SMC interchangeable.
BIF25 is currently under test and will ease operations by allowing all
commonly used spacecraft sub-system programs i.e. ROLLER1 SMC and SAOM to
be core-resident. This is achieved by deleting the program BURST, which
is not useful because of background variability and solar activity, and
re-configuring the program BOM as an interchangeable program. A modification
has been incorporated in the ME program MHER5 (Issue 2. p.6) to allow separate
accumulation of Argon and Xenon energy histograms and hence independent
variation of the collection times. This feature is available on board but
requires some ground support software change.
Design of a new ME application program MHER6 is complete, implementation
together with the appropriate ground support software for both MHER5 and
MHER6 is scheduled prior to the beginning of AO-2. MHER6 allows intensity
profile accumulations for offset and on-axis experiment halves within one
or two separate energy ranges, E1 < E < E2 and/or E3 < E <
E4 with time resolutions < 1 SWC(32 msec). Full information will be available
in Part III of the Observatory Users' Guide.
4. Observation Output
Final Observation Tape (FOT) production has been transferred from a
Honeywell to a Siemens computer, increasing both speed and efficiency of
production. While some delays occurred with the software conversion and
scheduling organisation, current FOT production is at day 23 for LE1/GSPC
and day 19 for ME. Some delays occurred in the production of GSPC/ME FOT's
because of the PM gain variation monitoring (ref. Section 1.2.4) and errors
in filing data from the new MHER5 mode. Despatch of tapes to PI's generally
occurs within 1 week of production and we are looking at methods of reducing
the gap between tape available at ESOC and in the hands of the PI.
Some observers have requested that the satellite pointing data during
slews be included on the FOT to maximise the use of the ME/GSPC slew data,
generated mainly for background correlation. Several bright sources have
been 'scanned', some known and others unexpected. A method of obtaining
the pointing history during slews is being investigated and will be implemented
on the FOT if feasible. Prior to this, slew history can usually be reconstructed
for specific requests from the manoeuvre history file data.
As expected, initial FOT production back-logs have now more or less
migrated through the Observatory system to appear as a back-log in automatic
analysis production further complicated by problems of ME energy channel
conversion and resolution functions and the general organisation of the
AUTO production system. Current production is at day 285 for LE1/LE2/GSPC,
and day 262 for the ME with some gaps because of tape reading problems.
Despatch of the auto output to PI's generally occurs about 2-3 weeks
after production. It is stressed that the raison d'etre of the automatic
analysis is to provide the observer with an overview of the results of the
observation (note the plans for interactive analysis) and that the output
is only 'scanned' by the duty scientists for obvious faults. It is neither
practical nor functionally necessary to subject the auto output to a rigorous
scientific examination and observers are particularly urged to heed the
various warnings in both output and documentation. Note that for the ME
spectral fitting is not presently incorporated in the automatic analysis
software.
In the LE automatic analysis an incorrect bin size factor for full resolution
images has produced source count rate underestimations which are a few
percent or zero for faint sources (20-30 photons) and up to a factor of
5 for sources with several hundred photons. Further details will be given
in the next EXPRESS and PI's whose prime LE observations are affected will
be informed directly.
Updating and improvement of calibration data has continued since the
launch. The calibration histories will be distributed on tape during March
to all institutes, and should be used instead of the calibration data on
the original AO-1 FOT's. Orbit history data for AO-1 will be included on
the same tape (because of errors in the orbit data on some early FOT's)
Documentation for the re-issue of the Final Observation Tape Handbook
(FOTH) is in the final stage of preparation and the complete FOTH should
be available during March. Included in the FOTH are notes on the LE and
GSPC automatic analysis, which have been distributed separately to all
AO-1 PI's (NB. one copy only to the hardware institutes). Equivalent notes
on the current ME automatic analysis are reproduced on p.31.
5. Future Plans
Efforts to schedule co-ordinated observations and the rescheduling of
those observations not correctly carried out during the high solar activity
from 16/2 to 22/2 have increased considerably the quantity of near real
time mission planning, nevertheless the time line has been published marginally
4 weeks in advance, viz. March 15th on 15/2 and March 31st on 27/2. The
complete AO-1 time line should be available by about mid-March. A number
of improvements have been incorporated in the mission planning software
and operations, and it should be possible to maintain such an advance time
line for AO-2. It must be emphasised that the mission planner or any other
observatory team member concerned with the advance planning of the observations
will accept inputs from the PI only (or a deputy nominated in writing by
the PI). Some recent examples of multiplexing in the input stream have
caused a high second derivative of the 'planning function' which can only
result in delays in the issue of the time line.
Documentation for AO-2 was issued at the end of January. A response
is required at the latest on 9th of March leading to evaluation and selection
of the AO-2 programme by mid-April.
The review of EXOSAT scientific operations at ESOC since launch has
been completed and it is intended to implement a number of changes. These
changes should streamline the operations, improve the working conditions
within the observatory, generate a better scientific environment and improve
the service to the scientific community.
With the addition of a further HP processor, more disc storage capacity,
extra terminals and by linking to the ESOC mainframe computer for CPU intensive
operations, a system will be provided to enable the visiting observer to
undertake interactive analysis of his data in the 48 hrs following the
observation. The observer will be able to call on the support of the resident
astronomers (duty Scientists) to assist him with the analysis.
The observatory team structure will be modified to provide a scientific
focal point within the team. Operations in the EXOSAT Dedicated Control
Room (real time EX2 system) will be undertaken by more operationally oriented
personnel, leaving the resident astronomers more time for work concerned
with calibration, auto analysis overview, interactive analysis support
and their own research programmes. Extra manpower will be devoted to mission
planning while an increase in the number of data aides should speed up
the more clerically oriented tasks.
These changes will be implemented over the coming months so that by
the first anniversary of routine operations the new system should be functioning
fully. A key element in the change is the recruitment of Duty Scientists/Observatory
Controllers and attention is drawn to the 'advertisement' on page 40. In
the next issue of the EXPRESS a fuller description of the observatory computational
facilities will be given.
Volume 4: OBSERVATORY STATUS AS OF 30th APRIL 1984
EXOSAT operations are approaching a triple milestone of '1 year in orbit,
1000 attitude manoeuvres and orbit number 100'. The programme of observations
approved by the Committee on Observation Proposal Selection (COPS) in
response to AO-1 is roughly 90% complete (about 700 observations), with
a further 70 scheduled in the period up to 29/5. Subject to COPS approval
the AO-2 programme should start on 30/5 and will include a small number
of outstanding AO-1 observations.
1. Hardware
1.1 Spacecraft
Reference is made to the article on p.30 for information on the spacecraft
hardware status. Note that the only combination of Reaction Control Equipment
(RCE) and Attitude and Orbit Control Electronics (AOCE) units which has
so far proved problem free is AOCE2/RCE1.
Erroneous OBC CPU overload errors, which normally have little impact
on operations, have on two occasions in the period 1/3/84 - 30/4/84 resulted
in the planned halt of the processor followed by a failure to re-initialize
one of the spacecraft application programs and hence a re-load of the complete
software system (duration approx. 90 minutes). For further operations a
modification has been introduced to overcome the initialisation problem
and avoid the necessity of re-loading. Additional testing and analysis
is required to determine the origin of these spurious errors.
1.2 Payload
1.2.1 LE1
PSD1 operations have been suspended following a degradation in the behaviour
of the 'LEP' (low energy pulses) first reported in Express
No. 3 p.5. Seven PSD1 observations were carried out in the period 1/3/84
to 30/4/84, viz. NGC 5548 day 62, Her X-1 day 64, CRAB day 73, IC 443 day
78,IC 443 day 80, Zeta Pup day 81 and GKP SNR day 114, giving an integrated
on-time since reactivation of about 30 hours, but showing a progressive
decrease in the times to LEP instability and increase to the arbitrary
safety limit (ref. section 2 p.4) of 6 c/s.
Operational procedures continue to ensure satisfactory performance of
CMA1. Note that observations are scheduled preferentially for solar aspect
(
) angles between 90° and 130° but some degree of latitude is possible
to accommodate coordinated or otherwise constrained observations.
There is no operation of the grating at present because of the partial
jamming of the mechanism.
1.2.3 LE2
All attempts (5) to re-activate CMA2 following the 'partial' operation
reported in Express No. 3 p.4 have proved unsuccessful.
Although no explanation exists for the failure, ideas of temperature
effects and mechanical contact problems have led to a strategy of maintaining
a cool detector (28V power supply line switched off) and operating the
detector exchange mechanism from time to time, so far to no avail.
PSD2 has remained non-operational.
As a functional test, the LE2 grating was successfully moved into and
out of the telescope FOV on 20/3/84.
1.2.3 ME
All sixteen proportional counters continue to operate satisfactorily.
Analysis of data from a repeat calibration observation of the CRAB NEBULA
on day 85 (note that the day 73 observation was affected by a high background
rate as a precursor to the solar storm on day 74) suggests that slight
gain increases (<~1-2%) of the Argon detectors have occurred since
the PV/Cal phase observation on day 275 (Xenon data is still in the process
of analysis). Leakage of gas from the detector is a possible explanation;
however this rate should have no significant detrimental effect on the
instrument performance during the mission lifetime. Additional analysis
is in progress and an electronic gain adjustment may be incorporated. P.I's
should at present assume a linear gain change throughout the period between
the two CRAB calibrations. Further information will be provided in an update
to the FOT Handbook and/or in a forthcoming issue of the Express. Regular
calibrations on the CRAB will be instituted.
1.2.4 GSPC
The GSPC hardware status remains stable and the detector continues
to operate satisfactorily.
A note on the gain variations introduced by the procedure of switching
off the 28V power supply line to LE1 in order to maintain a low detector
temperature is given on p.44.
2. Performance and Operations
Tables 1 and 2 give the current performance parameters of the EXOSAT
instruments based on the latest analyses of PV/Cal phase data.
PSD1 operations since re-activation total approximately 30 hours, however
each successive observation has shown a decrease in the useful observing
time as shown below:

Note that the first few observations (up to about 12 hours of total
'ON' time) were completed normally after the allotted
observing time, whereas all recent observations were terminated when the
LEP count rates increased above an arbitrarily defined 'safe' limit of
6 c/s. Similar procedures, clearly unsuccessful, of detector 'bake out'
using the gas system solenoid valves to raise the temperature (typically
by 25°C) together with a 'hot gas fill and drain have been carried out
between each observation with the aim of maximising the period of stable
LEP (2 c/s) and the time to increase to 6 c/s. From day 114 (GKP SNR) to
the next PSD observation scheduled on day 138 (NGC 6964) the detector will
remain drained in order to eliminate any effect of gas decomposition in
the orbital radiation environment.
Observatory operations were suspended on several occasions, during the
period 1.3.84 - 30.4.84. Two solar 'proton' events caused considerable
disruption to the planned time line. The first occurred on 14.3.84, 28
days ± a few hours after the event on 16.2.84 reported in Express
Issue 3 p.5, and reached a maximum particle density (>10 MeV) at
satellite altitudes of 100 cm-2 s-1 sr-1 i.e. a factor 6 on the earlier
activity from the same after the maximum. However, in comparison to this
event and Its predecessor, EXOSAT detected on 25/4 the onset of a huge
solar 'proton' event, which reached a maximum particle density (>10MeV)
of 2500 cm-2 s-1 sr-1 approximately one day later and prevented normal
operations for a period of 8 days. One sun safety mode trigger (see p.34)
and the erroneous OBC CPU overload errors (section 1.1) caused additional
loss of observing time.
A successful test of the orbit control system was carried out on 17/4
(ref. p.33). Certain restrictions will nevertheless apply for occultation
planning because of AOCS operational problems with the use of Reaction
Control Equipment (RCE) unit 2 which indicate that only RCE1 in conjunction
with AOCE2 is problem-free thus limiting the orbit control to one thruster.
To avoid unnecessarily high integrated dosage rates in a limited number
of channels of CMA1, the mission planning software now 'randomizes' the
position of point sources in the FOV of LEl within a ± 30 arc sec. square
of the normal pointing.
3. On-Board Software
Operational efficiency has been improved by the incorporation of a new
Basic-In-Flight Software system (BIF 25) which allows all commonly used
spacecraft sub-system programs to be core resident thus providing the maximum
6 slots for payload data processing programs. A further system update (BIF
26) will contain more powerful diagnostic facilities to aid the investigation
of spurious CPU overload errors (section 1.1).
Difficulties have been experienced with the operation of two new application
programs (MHER5/MHER6: Express Issue 3 p6), involving
triggering of telemetry overload errors under certain combinations of workspace
parameter definition and in conjunction with other application programs.
Further modifications incorporated in the software have solved the problem,
although precise limitations on time resolutions and telemetry load can
only be defined after sufficient operational use.
Since the launch of EXOSAT, 6 system updates (BIF 20 - BIF 25), 10 payload
application program modifications (update or new software) and 3 spacecraft
application program modifications have been carried out in response to
changing requirements as a result of the observational data analysis and
operational experience. It is anticipated that this level of activity will
shortly decrease.
4. Observation Output
Production of Final Observation Tapes (FOT's) is now routine and the
goal of approximately 20 days between observation and tape availability
at ESOC has been reached. Because of the iterative process of filing, analysis
and checking the data generated b,y modified OBC application programs,
production of certain FOT 5 containing eg. MPULS2, MHER5 (modified version,
Express No. 3 p6) data does incur a delay with respect
to the above 20 days.
Please note that P.I's are kindly requested to disregard the statement
in AO-2 Section 2 concerning copying and return of FOT's. ESOC do not require
return of the original tapes.
In response to requests from some users, the satellite attitude during
slew manoeuvres will be made available both in near real time to support
search of the ME/GSPC slew data for transient sources and unexpected variability
of known sources and on the FOT to allow observers to reconstruct the pointing
history throughout the manoeuvre. Slew auxillary data will be generated
immediately after a manoeuvre and an algorithm will be provided to determine
the satellite attitude using an interactive facility operated from a terminal
in the DCR. This auxiliary data will be stored on the FOT and a similar
algorithm will be supplied to enable users to extract the attitude data
using the relevant housekeeping telemetry format. Accuracy will be <~
5 arc minutes and the facility should be available within 2 to 3 months.
Details will be provided in an update to the FOT Handbook and/or in a forthcoming
issue of the Express. Note that it is not feasible to re-create the pointing
history systematically for manoeuvres carried out prior to the above implementation
but an analysis of archive tapes should in principle give the attitude
for specific requests only.
There have been one or two recent examples of mis-interpretation of
scientific data because of incorrect use of the real time EX2 graphics
facilities and observers are urged to treat all real time 'results' with
extreme caution. For example, integration of ME counts data will show a
significant excess of counts in low channels if the period of integration
covers detector switch-on or switch-off times when the gain is low. EX2
images, which are not linearized, should also be interpreted carefully,
particularly in view of the grey level scaling available and the known
off-axis point spread function.
Our general policy now is to perform the automatic analysis in three
priority categories viz:
Note, however, that software modifications are required before data
from new OBC modes such as MHER5, MHER6, GDIR, MPULS(1) and MPULS(2) or
from PSD1 observations can be analysed, implying that not all category
(b) analyses can proceed immediately.
AO-1 timelines have been published approximately one month in advance
up to the 'final' schedule covering the period 1/5-29/5. Note that Anne
Fahey has been assigned to mission planning duties as a full time task
and has been practically responsible for the preparation of all recent
time lines. Further changes in the division of responsibilities within
the Observatory Team are expected and will be described in forthcoming
issues of the Express. Considerable re-scheduling of omitted or disrupted
observations (eg. solar storms on 14/3 and 25/4) plus inclusion of previously
constrained AO-1 targets or coordinated observations have led to a solid
timeline to the end of May. A number of AO-1 observations will be outstanding
as of 29/5.
AO-2 proposal selection was undertaken by the COPS at their meeting
from 25/4 to 27/4 in ESTEC. Note that the total AO-2 response represents
an over-subscription for observing time of a factor of 9 for the six month
observation period. Successful proposers will be informed within the next
week or two.
Procurement of computer hardware and the definition of detailed requirements
for the interactive analysis system to be provided to enable visiting observers
to undertake a fuller analysis of their data immediately post-observation
is in progress. It is planned to give a description of the present and
proposed observatory computational facilities in the next issue of the
Express. Our goal is to have a working analysis system available for observers'
use by the end of September 1984.
In response to the second announcement of opportunity to participate
in the observation programme of EXOSAT 560 proposals were submitted for
the 6 month AO-2 observation period, a ninefold oversubscription in observation
time. Of the 560 proposals submitted, 191 comprising 450 separate observations
were selected as the approved A0-2 programme by the Committee on Observation
Proposal Selection (COPS) at their meetings on 25-27th April and 4-5th
May.
AO-2 observations have been carried out from the middle of June, with
a number of AO-1 targets interleaved and it is expected that the programme
will terminate around mid-December, again with outstanding or incomplete
observations because of later coordination or solar constraint.
A review took place at ESTEC on 4.6.84 of the failure/performance malfunction
history and current procedures for reactivation of specific elements of
the LE telescopes, namely PSDl, CMA1, PSD2, CMA2 and the LEl grating. No
firm conclusions were drawn regarding the reason(s) for any of the anomalies
observed. Comments on the operational procedures adopted in the attempts
to re-activate the various elements of the telescopes were principally
in the direction of extending the existing procedures. These are noted
in section 1.2.
All elements of the spacecraft hardware continue to operate as described
in previous issues of the EXPRESS. A number of points are noteworthy.
Spurious OBC memory parity error interrupts occur once or twice per
week with no impact on operations; however on one occasion during May the
frequency suddenly increased to approximately one per hour, remained at
the 'higher' level for 3 days and then suddenly decreased to the 'nominal'
rate. Although a small solar proton event ( >10 particles cm-2 sr-1
s-1 above 10 MeV) was in progress at the time, it seems unlikely that
this is a real correlation since EXOSAT has experienced much larger solar
storms (ref. Express Nos. 3 & 4).
Note that parity errors associated with a specific memory location have
been eliminated by appropriate re-arrangement of the on-board software.
No CPU overload errors have occurred since the commissioning of a new version
of the basic in-flight software (BIF26), although the frequency has in
any case been low.
In the first year of operations the available Solar Array power has
decreased by 5.5% from 288.5 watts to 272.5 watts. Note that the level
at which battery discharge would occur with all elements of the satellite
functioning normally is 227 watts such that if the present rate of degradation
is maintained (ref Express No. 4 p.40) sufficient
power should be available to ensure no interruption of operations prior
to re-entry into the dense atmosphere.
Between 14th and 28th June around the summer solstice, a scan of the
galactic centre (AO-1 observation, P.I.: Turner) was successfully carried
out, and involved 8 pairs of long slew sequences (90°) at the slowest slew
rate (43°/hr) covering the region of sky between b"= ± 5°
and l"= 0 ± 90°.
Although the procedure of 'bake-out' of PSD1 using the gas system solenoid
valves to raise the detector temperature typically from 25°C to 50°C, with
a subsequent gas fill and vent at the high temperature, has not maintained
the performance of PSD1 achieved immediately after re-activation (ref.
Express No.3 p.5), the recommendation of the ESTEC
review meeting was to continue this procedure with increased bake-out times
(>5 hours) and as a parallel activity, analyse in detail the data from
30 hours of PSD1 observations. These activities will commence immediately.
No operation of the grating is planned because of the partial jamming
of the mechanism; although the grating is clearly removed from the X-ray
beam, the available evidence suggests that it Is not fully In the 'out'
position and that the mechanism remains jammed with the grating at a few
degrees to the optical axis.
There has been no operation of LE2. Recommendations of the review meeting
are as follows:
All sixteen proportional counters continue to operate satisfactorily.
Attention is drawn to the discussion of ME background subtraction on
p.48, and the intention to re-introduce the procedure of swapping the array
halves between source pointing and background monitoring on specific targets
for which it is judged that slew data alone cannot provide the optimum
background subtraction. Note that because of a component failure in the
drive mechanism electronics of detectors E,F,G and H (Express
No. 3, p.4), the OBC time tag command facility is used to initiate
and stop movement of the detector quadrants E/F and G/H.
The GSPC continues to operate satisfactorily.
Methods of monitoring the gain variation of the GSPC caused by the systematic
switch-off of the 28V power supply line to LEl have been outlined in the
previous issue of the Express (No. 4, p.44).
Further analysis of the data has shown that the LED stimulation cannot
easily give an absolute gain calibration (conversion from LED ch. to
keV is non-deterministic) and observers are, therefore, recommended to
make use of the 4.7 keV feature (and the Bi lines) for absolute gain calibration
together with the LED channel for relative changes. There is, however,
preliminary evidence for evolution of the Bi lines and further information on the GSPC gain calibration will be described in the next issue-of
the Express.
3. On-Board Software
A new version of the Basic in-flight (BIF26) software, containing additional
diagnostic facilities to aid the investigation of the cause of spurious
CPU overload errors, is now in use.
Design is in progress of a revised ME direct mode application program,
similar In concept to the GSPC direct mode, in which the number of zero
samples of the energy channel is counted to define a time tag of each valid
event with an accuracy of the sample rate. Valid events can be selected
from within specified energy limits (ADC channels) to reduce background
and increase Sensitivity. Probably Argon data only would be selected
and the ME would be operated in the coaligned configuration. Details will
be given in a future issue of the Express and in an update to the FOT handbook.
4. Observation Output
Final Observation Tape (FOT) production is routine for all currently
supported operational modes of the P/L and the OBC, and the tape Is generally
available at ESOC within 20 days of the observation.
Considerable effort in the organisation, running, checking and dispatch
of automatic analyses has reduced the backlog reported in Express
No.4, p.7. Equivalent production is now at day 75 (1984), although
because of the priority given to the analysis of observations of non-hardware
group P.I's, analyses of a number of observations prior to day 75 are outstanding.
Spectral fitting, which is now included In the ME automatic analysis software
is scheduled whenever the source count rate is sufficiently high to provide
reasonable model fits.
Chapters 6-8 of the FOT Handbook, together with corrections to Rev.1
(chapters 1-5) will be despatched to all EXOSAT users as soon as possible.
The Observatory Team is well aware of the difficulties experienced by some
users because of lack of the appropriate documentation, production of which
was perhaps rightly not afforded the highest priority in the early phase
of the mission, and we will strive to improve this situation.
5. Future Plans
AO-1/AO-2 time lines continue to be published between 3 and 4 weeks
In advance, although the fairly late availability of the approved AO-2
programme with a series of early co-ordinated observations has meant that
some P.I's with observations during May and June may not have received
adequate warning of the schedule. Attention is drawn to the notes on p.6
describing P.I. interaction with the Observatory Team in the steps from
observation schedule to output despatch.
ESA Intends to publish the third announcement of opportunity to participate
In the EXOSAT observation programme (AO-3) during August, with expected
response in September and selection of the AO-3 programme in November.
AO-3 will have a duration of 9 to 12 months.
Volume 6: OBSERVATORY STATUS AS OF 31.8.84
Now that the majority of the Observatory Controllers recruited to execute
the real time operation of the Observatory have taken up their appointments,
the Observatory Team is almost up to full strength. The new staff are gradually
assuming responsibility for the operations after an initial period of training
in the DCR, and it is expected that this transition will be complete by
mid-October. P.I's and observers are reminded that the Duty Scientists
will continue to be responsible for all liaison work to establish P/L and
OBC configuration for the observations on an orbit-by-orbit basis and that
the Observatory Controllers will have full responsibility to carry out
the planned programme of observations. At the same time, the Duty Scientists
will be available or on call on a 24 hour per day rota, to support the
real time operations, principally for 'science' decisions, emergencies
and general assistance to the Observatory Controllers.
Full details of the Interactive Analysis System provided by the Observatory
Team to enable users to analyse their data at the Observatory will be given
in a future article in the Express. However, as we intend to 'go on the
air' by the early autumn, albeit in a preliminary fashion, a few general
remarks are made here:
- the system will support near real time analysis of data from the current
observation as well as analysis of the FOT's, if available, from prior
observations.
- non-hardware group P.I's and the Observatory Team will have priority
use of the system over 'hardware' group P.I's (the hardware groups being
Leiden, Leicester, Milan/Palermo, MSSL, Munich, Utrecht and SSD/ESTEC).
- booking of the system will be organized within the Observatory Team
by Susanne Ernst.
- the system will be available 24 hours per day; support and advice to
users will be provided by the Duty Scientists on a rota basis on call or
at ESOC between the hours of 08.00. and 23.00 everyday. On-call support
will mean telephone contact at home or by Eurosignal bleeper, and will
be requested at the discretion of the Observatory Controller. Note that
in principle, the Duty Scientist supporting the Interactive Analysis System
will also support the real time operations and that on-call support according
to speciality cannot be provided. Such support must be arranged on an ad
hoc basis with the relevant Observatory Team member.
Recent problems concerning mission planning serve to remind P.I's that
ephemerides should be quoted in the standard accepted form, that is the
time for phase zero, and that RA, DEC coordinates are for Epoch 1950. This
will always be assumed for communications from P.I's to the Observatory
Team and vice versa, unless specifically stated otherwise.
Attempts to re-activate the malfunctioning elements of the LE telescopes
(PSD1, PSD2 and CMA2) have been carried out in the previous two months,
all to no avail (ref. Section 1.2). These procedures will be continued
on a low priority basis although any success will, of course, be reported!
1. Hardware
1.1 Spacecraft
There is no change in the status of the spacecraft hardware. Spurious
OBC CPU overload errors and gyro drift jumps continue to cause minor inconvenience
but measures are being adopted to overcome this (ref. Section 3).
1.2 Payload
1.2.1 LEl
CMAl continues to function as described previously; attempts to reactivate
PSD1 by increased 'bake-out' durations (using the gas filling system solenoid
valves to increase the detector temperature) have proved unsuccessful in
that the onset of increasing LEP occurs soon after HT switch-on, and reaches
the arbitrary safety limit within a few minutes. Further analysis of the
existing data will be carried out with, eventually, a possible relaxation
of the safety limit.
1.2.2 LE2
Temperature cycling has had no effect on the status of CMA2; PSD2 has
been operated at zero residual gas pressure to determine whether the observed
anomalous behaviour is caused externally or internally. Preliminary analysis
suggests the latter. Further tests and analyses are in progress.
1.2.3 ME
The ME detector experiment status is unchanged; however attention is
drawn to the article on p.25 describing
the ME gain calibration and the observation of gain variation,
particularly in Argon detectors D + G, consistent
with minor gas leakage. Extrapolation of the present trends to the end
of the mission suggest that continuous operation of all detectors can be
maintained. Regular adjustment of the electronic amplifier gains to compensate
for detector gain changes has been instituted.
1.2.4 GSPC
The GSPC status is unchanged, but note the article on p.18
describing the instrument calibration.
2. Performance and Operation.
Tables 1 and 2 on p. 8/9 give the current performance parameters of
the EXOSAT instruments.
Station computer problems at VILSPA on 3/8 caused a loss of approximately
13 hours of observation time; several periods of loss of telecommanding
lasting about 30 minutes have occurred since then and are believed to result
from a power supply instability.
Since regular swapping of the ME array halves has been re-introduced,
the logical sequence of operation has been modified such that at no time
is the source not under observation, i.e. detector HT's are switched off
only for those detectors currently being moved. This avoids 'missing' flaring/bursts
from the source. Data produced during the period of swapping, although
correctly archived, is not at present written to the FOT because the observation
definition precludes periods of less than five minutes between telecommand
status changes. A modification to the ME FOT production software will be
incorporated as soon as possible. FOT's will be regenerated on request
for the intervening period (1984 Days 185- (?) 275), if it is suspected
that data from a source flare or burst may have been omitted on the original
FOT.
Recent long observations with the CMA (AR LAC, LE Background Cal.) of
48 hrs have demonstrated that the improved temperature stability of the
HT/detector combination has been maintained and it is clear that there
is no immediately obvious degradation in performance if the Al line Is
not switched off during periods of the order of one or two days. For GSPC
prime observations, when gain stability is essential, all Al lines (hence
GS HT) will therefore remain on during the manoeuvre to the source, provided
that total LE1 Al line on time (previous observation, manoeuvre, -GSPC
prime observation) does not exceed 24 hours.
Regular calibrations, with the Fe55 filter wheel source, of the CMA
low gain area and the new point source image area (ref. p.6) will be instituted.
3. On-Board Software
With the additional diagnostic facilities referred to in Express Issue 5, analysis of data from one
occurrence of the spurious CPU overload error
suggests a possible intermittent malfunction of the OBC instruction 'DPI'
- Disable Interrupt Processing. A new application program to monitor the
performance of DPI has been designed and will run continuously as a low
level background activity for several weeks to aid diagnosis of the error.
Because the Basic In Flight software requires all 16k of available
OBC memory and malfunction of one 8k 'module' is considered the most likely
failure mode, a special 8K version of the software was designed, developed
and commissioned prior to launch in order to avoid an unacceptably long
hiatus in operations in the event of a failure. This is the only 'design-for-failure'
situation. A major update to this 8k system to reflect some of the modifications
introduced since launch (BIF22 - BIF26) is in progress. Naturally, only
a subset of the facilities available in the current BIF26 can be provided
in the 8K version.
Modifications will be carried out to the two ME modes, MPULS and MPULS2
to incorporate a 128 channel energy histogram with 16 phase bins mode and
for MPULS2, Argon data only in the intensity samples.
Note that prior to release for general use, the revised ME Direct mode
application program first reported in Express
Issue 5 (p.6) requires a check using data from an observation of
the CRAB which is scheduled towards the end of September. Details of
this mode will be given in the next issue of the Express.
Gyro drift jumps during perigee continue to cause problems on reacquisition.
An application program will be designed to monitor and correct for such
jumps.
No other OBC software changes are planned and, once the above activities
are complete towards the end of October, the support for OBC software will
enter a maintenance phase until the end of the mission. Priority will,
of course, be given to failure/malfunction - driven modifications.
4. Observation Output
Automatic analysis production is currently at day 158 (equivalent, some
pre- day 158 observations outstanding) representing a delay of approximately
70 days between observation and analysis, although most non-hardware groups
receive their analysis output considerably quicker because of the priority
of running the analysis. Attention is drawn to the chronological list of
improvements in the ME automatic analysis software (p.35).
According to the original specification of the FOT, the auxiliary data
contain a set of information relating to a period of stable pointing. Recently,
with the incorporation of slew attitude data into auxiliary data, this
situation has changed (details in the new FOT Handbook). To ensure that
slew attitude data is correctly aligned with slew observation data and
at the same time, correct other outstanding anomalies, a redefinition of
the procedure for incorporating auxiliary data onto the FOT is in progress.
In the meantime, a number of anomalies concerning the merging of auxiliary
data onto FOT's are hereby summarised:
- the start and end times of a stable pointing (given in auxiliary data)
are not always correctly correlated with the start and end times of observations
on the FOT. The times themselves are correct; occasionally, however, the
A4 data for the following pointing is wrongly merged with the telemetry
for the current pointing.
- since June 11th 1984, FOT's contain slew attitudes for the slew following
a pointing, but not for the preceeding slew.
- if an attitude trim manoeuvre is made during an observation, there
will, correspondingly, be more than one set of A4 data. The exact time
of the trim should be deduced from the start and end times of each auxiliary
data set. It should not be deduced from the information called "guide
star coordinates" contained in the observation directory, because
this will lead to slightly incorrect values.
- if an attitude slew is made during an observation, there will be more
than one set of A4 data, and in this case the manoeuvre times can be obtained
either from the auxiliary data or from inspection of the "slew busy"
flag in the observation directory.
Calibration data on FOT's for all experiments has been updated and refined
during August (or early September, in some cases). and should be used for
-the analysis of all FOT's. The new data sets can be identified by the
"time of last update of calibration history" in record 1, which
should be August or September 1984, eg. as described in the article on
p.25. FOT's generated at ESOC from early September will contain updated
CCF's.
5. Future Plans
As from orbit 124, the pointing direction of the spacecraft will be
modified such that point sources are imaged by the LE1 CMA within a ±
30" randomization area of X = -60, Y = -18 in order to avoid high dosage
in the detector 'low gain' pixels (Express
No.5 p.5) . This represents a
move towards the centre of the telescope FOV of ~2', whilst maintaining
the maximum GSPC/ME response.
The AO-2 programme of observations should terminate during December
1984, although a number of coordinated observations cannot take place until
1985 and other targets only then emerge from the solar constraint. In addition
about 19 AO-1 observations are outstanding. Regular calibrations (CMA low
gain area, ME Detector gains, GSPC gains etc.) will stretch the nominal
AO-2 programme further such that AO-3 observations are expected to begin
during January 1985.
ESA is currently specifying the establishment of the EXOSAT data archive
including the procedure for access and, once the design is implemented,
retrieval will be possible for data designated as public. Details will
be given in a future issue of the Express.
A number of long LE prime observations (> 6 units, but excluding
deep fields) have shown no significant source detection after 3 units.
Therefore In view of the real time response capability of by EXOSAT and
the need to maximise the scientific return through significant results,
such observations will in future be terminated after 3 units following
discussion between the duty scientist/project scientist and, if possible,
the P.I. This procedure will be executed sparingly.
Volume 7: OBSERVATORY STATUS AS OF 31.10.84
EXOSAT has been operational for 17 months, approximately one half of
its natural lifetime as noted in the foreword, with 677 of the 717 approved
AO-1 pointings and 236 of the 470 approved AO-2 pointings completed. AO-2
observations together with the small number of outstanding AO-1 pointings
will continue until January/February 1985, although the solar constraint
and later co-ordinations preclude several AO-2 targets from the formal
observation period.
1. Hardware
There have been no changes in the status of the spacecraft or payload
hardware.
Measurements of observed star separations in the star tracker field
of view compared with the accurately known catalogue positions have shown
that a systematic error in the star tracker calibration reference points
(Local Lord Points) exists. Depending on the position of star 1 In the
FOV, this can introduce a bias in the pointing direction of the Instruments.
Typical values would be 2-3" with worst-case figures (star 1 near
edge of FOV - 1.5 deg. from centre) of 8". Measures are in hand to
determine and correct this bias, in the meantime Investigators publishing
position data should verify with the Observatory Tean the likely maximum
error in the result. Note that overall pointing errors are currently quoted
as 10", which assumes no contribution from errors in the ST reference
point coordinates.
Attempts to re-activate the malfunctioning elements of the LE telescopes
have not been successful; PSD1 continues to exhibit rapidly increasing
LEP (low energy pulses) very soon after HT switch on, although the initial
value is always nominal at ~2 c/s. Temperature cycling and variation of
the plate HT's has had no effect on the operation of CMA2. PSD2 has been
operated (HT on) a number of times at 0 mb residual pressure with no indication
of external breakdown, however regulation pressure operation (1100mb) immediately
shows the anomalous behaviour originally observed (high count rates: Emax,
Guard and qualified events).
Additional tests will be carried out during the next few weeks on these
detectors, namely the activation of a 'glow discharge' In PSD2 (operation
in the corona region in an attempt to clean the Internal electrodes - ?
remove the ubiquitous speck of dust), continuation of the thermal cycling
once per orbit on CMA2 and, somewhat dependent on PSD2 results, a relaxation
of the safety criterion for PSD1 operation and/or a 'glow discharge'.
A re-calibration of all ME detectors on the CRAB (ref. p.12) has verified
the gain variation first reported in Express
Issue 6 (p.4). Argon detectors
D+G show the strongest trend (<~12.5% per year) which can, however,
at the present rate be adequately compensated throughout the mission by
electronic gain adjustment.
2. Performance and Operations
Tables 1 and 2 give the current performance parameters of the EXOSAT
instruments.
During the period 1/9 to 31/10, loss of observation time (10 hours)
occurred on two separate but related occasions when safety mode of the
AOCS was triggered, principally because of procedural errors. Certain additional
checks have been introduced to reduce the likelihood of re-occurrence.
Observation time (~3 hrs) was also lost when a cable short circuit caused
a local fire at Vilspa, however prompt action by the Vilspa staff prevented
any serious disruption. Ground system procedural problems have caused errors
In the OBC software operation leading to a further loss of observation
time of approximately 6 hours.
Available power from the solar array has dropped from an average 280
watts to an average 270 watts over the period July 1983 to July 1984, i.e.
a rate of decrease <~ 4% per yr, which would be sufficiently
low to maintain operations with an adequate margin for a 4 year mission.
Preliminary estimates of fuel consumption (propane) from launch to the
present, based on careful logging of a sample of slews, fine pointing and
non-routine operations, suggest that the margin may not be sufficient to
guarantee operation during the final months of a 4 year mission unless
minor measures are taken immediately to conserve fuel (ref. p. 5 under
'Future Plans'). It is emphasised that the figures are provisional and
detailed calculations are required on all slews, fine pointing etc., before
a definitive statement on fuel usage can be made (an article on this subject
will be included in the December issue of the Express).
Since the beginning of the mission, problems have been experienced with
Y-axis slews at the highest slew rate (170.7 deg/hr). In some cases, these
slews which do not proceed normally (as determined by monitoring of the
Y-gyro) are terminated and restarted, leading to unnecessary fuel consumption.
Marconi Space Systems (MSS) have performed several hundred slew simulations
reproducing this behaviour and have defined a procedure such that interruption
of the slew is unnecessary. This is currently being implemented at ESOC.
Note, however, that from December 15th, the 170.7 deg/hr slew-rate will
not be used (ref. p. 5).
Issue 4 of the Express (p.34) described
a problem encountered with the redundant Attitude and Orbit Control Electronics
(AOCE 2) which has been in use since August 1983, whereby a spurious value
of the gyro drift compensation on the Y-axis can be produced when the star
tracker error coordinate changes sign. Offsetting the limit cycle by 5
arcseconds on the Y-axis has 'solved' the problem, but investigations by
MSS now show that this anomalous behaviour can be explained by a non-nominal
component characteristic which gives rise to an erroneous "read"
of the star tracker data.
Also reported in the same issue of the EXPRESS was a phenomenon encountered
occasionally during perigee passage when the gyro drift biases (GDB) on
the Z- and S-gyros spontaneously change level. An OBC program has been
developed to monitor the GDB levels on all gyros and reset them If jumps
occur. The program is activated prior to Loss of Signal (LOS) each perigee.
EXOSAT's second eclipse season, covering a period of 12 orbits with
eclipses varying in duration from a few minutes to approximately 1 hour,
has just ended.
3. On-Board Software
Now that all planned modifications to the on-board software are complete,
maintenance of the system, including further development to cover malfunctions
or new requirements, will be undertaken within the context of a software
maintenance support contract of approximately 0. 2 man-year of effort.
Emergency situations will be dealt with on an ad hoc basis. Reference is
made to the article on p. 30 describing the revised ME.Direct mode application
program.
4. Observation Output
A recent problem with the tape archiving system on the general Multi-Satellite
Support System (MSSS), when approximately 7 hours data was irretrievably
lost, serves to encourage P.I's to quickly scan through FOT'S on receipt
and inform the Observatory promptly of any anomalies. Archiving has been
carried out as follows: 1600 bpi archive tapes are produced in real time
from the incoming telemetry stream, kept in a cyclic pool for a certain
period and then copied to 6250 bpi master archive tapes. Until the present,
this system has proved error free but a fault in the copy process discovered
after recycling has illustrated an inherent weakness of the system. Steps
have been taken to extend the size of the cyclic pool such that tapes have
normally been delivered to the P.I. and the auto analysis carried out by
the Observatory prior to recycling. Additional security checks have been
implemented in the copying process from real time to master archive tapes.
P.I's should nevertheless check their FOT as soon as possible after receipt
for any gross structural errors, e.g. expected packets all present etc.
The FOT handbook has been completely revised and extended to include
a comprehensive chapter on data processing and scientific analysis. In
attempting to present as complete a picture as possible we have regrettably
required considerably more time than anticipated but the final document
is now ready for despatch.
Note that the majority of modifications to the real time graphics software
have been completed and, as for the OBC software, maintenance support only
will be available in the future.
5. Future Plans
Preliminary estimates of fuel consumption (propane) from launch to the
present suggest that sane conservation may be necessary to maintain operations
during the last months of a 4 year mission. This presents, of course, a
difficult trade-off since the state of the hardware in mid-1987 is not
easily predictable, therefore a minimal adjustment to the procedures will
be instituted immediately to ensure as far as possible a slightly positive
fuel margin extrapolated to May 1987. Refinements to the model and additional
calibrations are in progress and may lead to further conservation measures.
As from 15.12.84 the following slew strategy will be adopted, pending results
of the more detailed calculations:
- no slews at 170.7 deg/hr.
- reduced number of slews at 85.3 deg/hr consistent with maintaining
the observation programme.
- Use 42.7 deg/hr as the default slew rate.
On average, manoeuvre durations will be increased by a few minutes as
a result of the above.
Now that EXOSAT is half-way through its natural lifetime, a detailed
study is in progress to identify an optimum strategy for lifetime extension
beyond April 1986 using the hydrazine originally foreseen for orbit modification
for occultations. Occultation measurements are not now the prime thrust
of EXOSAT although a small number may be carried out during the next year
and, in preparation for this, a 'natural' occultation is planned towards
the end of this year. Clearly, any use of hydrazine for occultation will
reduce the possible lifetime extension and a trade-off must therefore be
made. Further details will be given in a future edition of the Express.
P.I's with approved coordinated observations are urged to define as
precisely as possible the times of coordination of their EXOSAT observation
with other facilities such that the Observatory tean can adjust the EXOSAT
schedule when necessary and still maintain the actual coordination.
Volume 8: OBSERVATORY STATUS AS OF 31.12.84
EXOSAT's third programme of observations (AO-3) will start during February/March
1985 and has a planned duration of 12 months. Outstanding AO-2 pointings
(~110 of the 470 approved) will be completed in January/February or interleaved
with the AO-3 programme.
1. Hardware
At 09.18Z on Day 366(84) the X-gyro motor current increased from its
nominal value of ~70 ma to ~200 ma within one telemetry format (8s). The
current remained high, fluctuating between ~180 ma and 276 ma (full scale
on the analogue read out) and the X-gyro health monitor switched from
'GOOD' to 'FAIL'. Since gyro selection was on the basis of the health monitor,
the S (Skew)-gyro was autonomously selected. De-pointing of the spacecraft
occurred on all three axes as a result of the S-gyro selection. Periodic
switching on of the X-gyro heater by its temperature control circuit
was observed for several minutes after the gyro motor current increase,
however this behaviour ceased and a short time later the temperature of
the gyro box increased. On this basis, the gyro selection logic was changed
from 'health monitor' to "SYZ" and the X-gyro switched off. Safety
mode was triggered at this point (Y-axis pointing at the sun) with an indication
that excessive rate had been detected but this was later diagnosed as spurious
incremental signals generated by the X-gyro switch off.
A short test of the X-gyro was carried out while the spacecraft remained
in safety mode. The gyro was switched on for approximately 7 minutes, throughout
which the motor displayed a similar behaviour as earlier and the health
monitor remained at 'FAIL'. During the switch on and off the Y-axis rotation
rate changed, consistent with a momentum exchange between the spacecraft
and X-gyro on the assumption that the X-gyro was spinning at its nominal
rate.
There have been no changes In the status of the payload hardware. Additional
calibration tests on the GSPC (ref. p. 25) have led to refinement of the
effective areas and a re-definition of the background line feature energies.
2. Performance and Operation
Tables 1 and 2 on p. 5/6 give the current performance parameters of
the EXOSAT instruments.
During the period 1.11.84 to 31.12.84 loss of observation time has resulted
from ground computer system problems (3 hrs, Day 310), a power failure
at ESOC (3 hrs, Day 334), solar activity (3.6 hrs, Day 355) and the X-gyro
malfunction on day 366 (~16 hrs).
Regular swapping of the ME detector array halves was reintroduced (ref.
EXPRESS no. 6 p. 4) to provide optimal background subtraction
for weak source observations. This procedure is now the default for all
observations, and P.I.'s should inform the Duty Scientist responsible for
the orbit preparation if array swapping is not required.
A number of problems have arisen during source observations with respect
to the requested payload configuration or OBC modes, e.g. a detection of
a weak extragalactic source with the Boron filter without first using the
Lexan filters. The following general configuration conditions are considered
as standard:
- Medium energy experiment array half is always offset with an array
swap as above (typically once/unit).
- Weak sources must be observed initially with a Lexan filter and detected.
- Photometry using the low energy telescope will be performed only
with a Lexan filter.
Note that responsibility for the final decision on configuration rests
with the Duty Scientist/Observatory Controller who will be familiar with
the science of the proposal and all payload/OBC operational details.
3. Observation Output
P.I's are reminded that the Observatory will despatch 1 copy only of
the FOT per observation. There are no exceptions to this rule and P.I.'s
must themselves ensure the distribution of data as appropriate to their
Co.I.'s.
Chapter 8.2 of the revised (Rev. 2) FOT Handbook, dealing with ME data
analysis, will be despatched shortly together with a number of single page
updates to Rev. 2.
4. Future Plans
A 'natural' occultation of 4U1530-44 is scheduled for 16.01.85. This
will provide a thorough test of the ground system software and operations
procedures necessary to carry out occultations. Following this, a decision
will be taken on the execution of a small number of approved AO occultation
observations.
Specification of the concept and design of software for the generation
of the EXOSAT observation log is in progress The function of this log is
to provide a ready means to inform the community of the EXOSAT observation
programme and to enable the Observatory Team to request information about
this programme.
Software implementation and generation of the log is planned for early
sumner 1985, such that public access to EXOSAT data can be supported in
an efficient manner.
Data from PV/Cal and certain AO-1 observations will become public in
April 1985. The observation log will identify which data is currently available
and listings will be published in the EXPRESS.
[EXOSAT Home]
[About EXOSAT]
[Archive]
[Software]
[Gallery]
[Publications]
Page authors: Lorella Angelini Jesse Allen