The total amount of time allocated to General Observers during NuSTAR
Cycle 12 is expected to be 11.7 Ms (~73% of the total available
observing time). This
NASA Research Announcement (NRA) solicits General Observer (GO)
proposals for NuSTAR, with approximately 8.5 Ms of observing time
available during the period from June 1, 2026, to May 31, 2027.
Observing time will be made available to scientists at both U.S. and non-U.S.
institutions (except the People’s Republic of China). Individuals may
submit proposals for three general types of observations:
"standard-mode", "Target-of-
Opportunity" (ToO), and "Large Programs".
An additional 3.2 Ms will be allocated to joint programs through
other observatories.
The remaining ~27% of the observing time will be allocated through the NuSTAR
Project to the
NuSTAR legacy survey observations (2%); NuSTARPI discretionary
time (15%), including unsolicited ToO observations open to the scientific community;
and time reserved for calibration observations, engineering tasks, and resolution of
operational issues (10%).
NuSTAR data from approved GO program observations (including
peer review approved ToO observations) have a nominal six-month
exclusive-use period commencing at the time of receipt of the
processed data by the observer.
Note that Principal Investigators (PIs)
may ask for waivers that increase (or decrease) the default exclusive-use period.
Waivers should be on a case-by-case basis, infrequent, and always with compelling
justification. Data resulting from unsolicited ToO requests will have no exclusive-use
period.
Phase-1 (observing) proposals recommended for implementation, the approved target
observations will be assigned a Category A, B, C or L (L designates a
Large program
target) and a recommended exposure time. Note that for proposals
including observations of multiple targets, the priority of each target observation will be
separately categorized. Assuming nominal operational efficiency, it is anticipated that
observations of most standard-mode Category A, B or L targets will be carried out
during Cycle 12. Any standard-mode, non-time-constrained Category A, B or L
observations not observed during Cycle 12 will be carried over to Cycle 13.
Observations of Category C targets will be executed on a best-effort basis. Category C
targets not scheduled during a particular observing cycle will not be carried over to the
succeeding cycle; such observations may be re-proposed to a future observing cycle.
It is anticipated that no more than $4M in funding will be made available to support the analysis of targets accepted at priority L, A, B or C.
Only PIs affiliated with, and located
at, a US institution will be eligible for funding for accepted
NuSTAR proposals through NASA.
As part of the NuSTAR
Cycle 12 program, up to 1.5 Ms of XMM-Newton observing time, up to
150 ks of Swift observing time, and up to 500 ks
of XRISM observing time will be made available for
coordinated observations with NuSTAR. For more information on
joint programs, please see this page.
New: For Cycle 12, a total of up to 500 ks of XRISM observing time will be made available for joint
observations with NuSTAR.
New: For Cycle 12, The minimum response time that may be specified for NuSTAR ToO observations is now < 24 hours, and such a rapid response time must be clearly justified in the proposals. This has been made possible by the development of an automated system that responds to the triggering of these observations, potentially repointing NuSTAR to a ToO target within 6 hours.
New: The scientific justification for all proposals must now include a one-paragraph anonymized work plan.
No IXPE observation time is made available in NuSTAR Cycle 12, though proposals may request coordinated
observations with already selected IXPE proposals. Joint NUSTAR / IXPE proposals may be submitted to the IXPE GO program.
Note that proposers requesting coordinated NuSTAR Cycle 12
observations with any facility have to provide a clear scientific
assessment of the need for the NuSTAR exposure, also for the case
that coordinated observations turn out not to be possible:
Should the NuSTAR observation(s) still be performed? What are the
scientific objectives if no coordination is possible?
The phase-1 proposal review will be done in a dual-anonymous fashion.
The overarching objective of dual-anonymous peer review is to reduce bias in the
evaluation of a proposal. Under this system, not only are proposers unaware of the
identity of the members on the review panel, but the reviewers do not have explicit
knowledge of the proposal teams.
Proposers should consult the Guidelines for Proposers to ROSES GO/GI DAPR
Programs under "Other documents" on the NSPIRES page for this program element for
instructions on writing proposals appropriate for dual-anonymous peer review. The
instructions here and in that document supersede the default instructions given in the
NASA Grant and Cooperative Agreement Manual (GCAM) and the ROSES Summary of
Solicitation. Proposers will also be required to upload a separate "Expertise and
Resources Not Anonymized" document, that is not anonymized. The "Guidelines for
Proposers to ROSES GO/GI DAPR Programs" contains complete information on how to
write this separate document.
To meet the objectives of dual-anonymous peer review, review panels will be instructed
to evaluate the anonymized proposals, without initially taking into account the proposing
team’s qualifications. As a final check, and only after the evaluation is finalized for all
proposals, the panel will be provided with the "Expertise and Resources Not
Anonymized" (E&R) document. The panel will review the E&R document to validate that
the proposers have the qualifications and capabilities required to successfully execute
the proposed science investigation.
Proposals should eliminate language that identifies the proposers or institution, as discussed in the Guidelines for Anonymous Proposals.
PIs are required to upload a one-page "Team Expertise" PDF
through ARK as a separate upload when submitting the anonymized
Scientific/Technical/Management section. (Note that, for NuSTAR
proposals, the page limit for the team expertise document is one page,
i.e. further constrained compared to "no more than three pages" from
the general guidelines document.)
This document provides a list of all team members, their institutional
affiliations, roles, expertise, and contributions to the work. The
document should also discuss any specific resources that are key to
completing the proposed work.
If a change of the exclusive-use period from the 6-month default is requested (expected to happen infrequently), a compelling justification e.g., protecting the timely completion of a graduate student's thesis, needs to be added in this document.
NASA understands that dual-anonymous peer review represents a major shift in
the evaluation of General Observer / General Investigator proposals, and as such
there may be occasional slips in writing anonymized proposals. However, NASA
reserves the right to return without review proposals that are particularly egregious
in terms of the identification of the proposing team.
Phase-1 proposals will be evaluated by a peer evaluation panel for Merit and Relevance
(see Section V(a) of the ROSES Summary of Solicitation), and the evaluation of merit
includes:
The extent to which the proposed investigation complements and enhances the
anticipated science return from the NuSTAR mission
The suitability of using the NuSTAR observatory and associated data products for
the proposed investigation, including the degree to which the investigation exploits
the unique capabilities of NuSTAR
The feasibility of accomplishing the objectives of the proposed investigation with
the requested observations, including the degree to which the proposal satisfies
NuSTAR observational constraints and the feasibility of the proposed analysis
techniques
For joint observing proposals, the relevance and feasibility of the corresponding
XMM-Newton, Neil Gehrels Swift or XRISM observations
The degree to which the proposed observation(s) places demands upon mission
resources
In the case of ToO proposals the justification of the trigger probabilities
A total of up to 2 Ms of NuSTAR Cycle 12 observing time will be made available for the
Large Program (LP) category. The minimum total exposure time for LP proposals is 500
ks, and such proposals are allowed an additional page of text to describe the proposed
program.
Data from approved Cycle 12 LPs will have a nominal six-month exclusive-use
period after which the data will be placed in the public archive.
An LP may be a ToO but
it can only have a single trigger (e.g., where a long observation is needed after an initial
trigger).
A total of up to 1.5 Ms of NuSTAR Cycle 12 observing time will be made available for
proposals to observe ToOs.
Proposers interested in submitting ToO requests should note the following:
Proposals must provide exact, detailed trigger criteria and a credible estimate
(including justification) of the probability of triggering the ToO during Cycle 12
(and Cycle 13 for multi-year proposals)
The minimum response time that may be specified for NuSTAR ToO observations is < 24 hours, and such a rapid
response time must be clearly justified in the proposals. This is because an automated system is now in place to respond to the triggering of these observations.
The standard ToO response time for NuSTAR ToO observations remains 48 hours to 1 week.
The observations must have an astrophysical trigger and be designated as
Category A
Proposals for ToO observations that can be triggered from a class of objects or
set of potential targets are permitted
Active ToO programs submitted to the Chandra/NuSTAR,
XMM-Newton/NuSTAR, Neil Gehrels Swift/NuSTAR,
or IXPE/NuSTAR GO Program Calls for Proposals approved
prior to the Cycle 12 solicitation will take precedence over NuSTAR Cycle 12
proposals with the same targets and trigger criteria.
ToO proposals selected as part of the NuSTAR Cycle 12 GO program will take precedence over
unsolicited ToO’s and may replace already scheduled observations, even those coordinated with other observatories.
In the case of Large Program ToOs with multiple observations, only the initial
observation is counted against the 1.5 Ms maximum ToO exposure time (since
subsequent observations are considered to be monitoring observations).
Multi-year ToO programs may be triggered in Cycle 12 or Cycle 13. Accepted Cycle 12
ToO observations not designated as multi-year can only be triggered until the end of the
cycle and observations not triggered during Cycle 12 will not be carried over to Cycle
13. Such observations may be re-proposed to a subsequent cycle. Data from approved
Cycle 12 ToO observations will have a nominal six-month exclusive-use period after
which the data will be placed in the public archive.
Proposals may request that observations (including ToO observations) be scheduled over a
two-cycle period. Multi-year programs must be strongly justified in the proposal text.
If a multi-year program, in particular one including ToO observations, is not strongly justified
in the proposal text it might be evaluated as a Cycle 12-only proposal. No multi-year
programs awarded in Cycle 12 will be carried beyond Cycle 13, i.e., all observations
must occur in Cycles 12 and 13. Multi-year joint programs with XMM-Newton or Neil
Gehrels Swift may also be proposed. However, no XRISM observing time is allowed for multi-cycle proposals.
All approved multi-year programs must
be category A, B or L. It is anticipated that Cycle 13 will commence on June 1, 2027,
and tentatively have a duration of one year.
Time-constrained observations are defined as observations that must be performed
within a specific time window. This includes phase-constrained observations and
coordinated observing campaigns with ground-based or space-based facilities. Time-
constrained observations are subject to the following limitations:
Time-constrained observations designated Category A, B or L will be given
highest priority for scheduling during Cycle 12 (or Cycle 12 and 13 for multi-year
programs). Time-constrained observations of Category C targets will be executed
on a best-effort basis and therefore should be scientifically justified if the time
constraint is not satisfied.
The time constraints for multi-year programs can occur in Cycle 12 and/or Cycle
13.
Time-constrained Category A, B or L observations that are not part of a multi-
year program and are not scheduled during Cycle 12 may be carried over to
Cycle 13 where warranted by scientific or operational circumstances (e.g., in the
case of coordinated observations with other space- or ground-based
observatories). Category C time-constrained observations not scheduled during
Cycle 12 will not be carried over to Cycle 13.
Monitoring programs are defined as investigations requiring two or more
observations of the same target, each of which is considered a "visit".
For such programs, the time interval between successive visits must be ≥ 14 hours. Note that all monitoring programs are designated as time constrained.
Proposed Neil Gehrels Swift observing time can include monitoring that
precedes, follows, and/or (for ToOs) triggers NuSTAR observing time.
For coordinated or time-constrained observations, it is the proposer's responsibility to
inform the NuSTAR SOC of the observing time windows as soon as possible, but at a
minimum of one month before initiation of the observations. In cases where
observations involve coordination with other space-based observatories, the NuSTAR
SOC will be responsible for communicating detailed schedule constraints with the
relevant operations team(s).
Additional details concerning Cycle 12 are given in the NuSTAR NRA.
There will be a two-phase proposal process. Phase one is for observing proposals. Phase two is for budget proposals for successful phase one proposers who were awarded priority L, A or B targets. Only observing proposals will be accepted at this time.
Proposal submission is done via the
HEASARC ARK/RPS on-line system. Hard-copy submission is not required. The following
elements are required:
Proposal form (cover page & general form, and one or more
pages of the Target form) generated by, and submitted through, ARK/RPS.
Anonymized Scientific/Technical/Management section in PDF format,
not exceeding 4 pages for a Regular
and 5 pages for a Large Program
and/or Joint Program proposal, to be uploaded through ARK/RPS.
Note that the list of references does not count against these page
limits, i.e, the PDF may have one more page, only to include the
list of references.
One-page "Expertise and Resources - Not Anonymized" PDF is
requried through ARK as a separate upload when submitting the
anonymized Scientific/Technical/Management section. (Note that, for
NuSTAR proposals, the page limit for the team expertise document is
one page, i.e. further constrained compared to "no more than three
pages" from the general guidelines document.)
The following should not be submitted:
The PI's institution's own cover page.
Supporting material (e.g., pending/current support).
Formatted electronic copies of the ARK/RPS form.
Hard copies of any of the above, including electronically
required elements.
We provide below some key details for NuSTAR Cycle 12.
For further details, consult the
ARK/RPS help file.
Cover Page
Institutional endorsement is not required by NASA
in NuSTAR phase 1 proposals. Use the endorsement-related
entries only if they are required or desired by the PI's
institution.
A total of up to 2 Ms of NuSTAR Cycle 12 observing time will
be made available for the Large Program (LP) category. The minimum
total exposure time for LP proposals is 500 ks.
Joint proposals for NuSTAR observations
with Chandra or IXPE
cannot be submitted in response to this AO.
However, NuSTAR does have separate agreements
with Chandra and IXPE for coordinated
observations. Please see the
the joint programs through other observatories section of the Proposals and Tools page for
more information.
To facilitate checking for conflicts of interest during the peer review process, the co-I's institution must be chosen from the menu (thereby enforcing a uniform set of names). Please check the list of institutions and contact
the RPS team as soon as possible if your co-I's institution is not on this
list.
Up to 30 co-investigators can be entered into the RPS form. However, only the first 15 co-investigators will appear on the cover page PDF.
The full list will be used by project personnel for
conflict checking. Under the Dual Anonymous Proposal Review Procedure
reviewers will not see any investigator names provided to ARK/RPS,
unless they assess them after ranking the proposals (see the DAPR
Guidelines). Please do not enter any investigator names in any ARK/RPS
comment fields.
Proposals involving bilateral work with the People's Republic of China (PRC) and
proposals directly from PRC organizations and/or with a PI affiliated with a PRC
organization, are not eligible and will be declined without review. For more information
see Section III.c of the ROSES Summary of Solicitation.
Target Form
Time Constrained: A target is considered as "Time Constrained" if any of the following sections of the target form are marked as 'Yes':
Position angle dependent
Monitoring Program
Phase Dependent
Date Constrained
Multi-year
See the NuSTAR RPS help page for more information about these fields.
In addition, observations coordinated with other ground- or space-based
observatories are considered as time constrained.
Proposers should include a summary of details that are
necessary for scheduling and observation planning (constraints,
observing mode) in the Remarks box for each
target.
Sources with fluxes > 10-11 ergs s-1
cm-2 within 5° of the target may cause increased non-uniform
background gradients due to stray light. Users should check observations for
potential stray light contributions using the tool that is available
at the NuSTARSOC web site. If a field is designated as having a "Potential stray light issue", proposers should submit a request for a feasibility analysis to nustar-help@srl.caltech.edu at least 2 business days prior to the proposal submission deadline.
The minimum exposure for NuSTAR targets is 20 ks. If
the proposer is also requesting XMM-Newton, XRISM,
and/or Swift time, the minimum exposure times for these
telescopes are 5 ks, 10 ks, and 1 ks, respectively.
Estimated Count Rates:
Expected total band (3-79 keV) count rate of the source in counts/second for both modules in a 50% PSF extraction with no deadtime.
Target of Opportunity (ToOs):
A total of up to 1.5 Ms of NuSTAR Cycle
12 observing time will be made available for proposals to observe
ToOs. Single-trigger ToOs that are part of a Large Program are not
held to a 1.5 Ms exposure time limit. Please note that regular ToOs do not
carry over into Cycle 13.
For ToO observations that are to be triggered from a class of objects:
Complete one target form per trigger only, specifying "0.0" for both
the R.A. and Dec. fields and providing a generic target name, and, if
applicable, enter a list of potential target names in the ToO Remarks
field. If the list of targets is too long to fit in the TOO Remarks
field, include the list in the anonymized
Scientific/Technical/Management section instead and put a note in the ToO Remarks to look there for the list.
For ToO observations that are to be triggered from a list of specific named objects: Complete one target form per object and trigger criterion even if you ask for time for a subset only. For each ToO proposal the "Maximum Total Time Requested for ToOs" field must be provided. If you ask for time for a subset only, this number will be smaller than the automatically calculated summed exposure time for all target forms.
Please note that it is the responsibility of the PI of an
accepted ToO proposal to alert the NuSTAR SOC when the trigger
conditions for their accepted ToO have been satisfied (via
http://www.nustar.caltech.edu/page/too_policy).
After completing all fields for a proposal in ARK/RPS, use the
Verify button to confirm
that all required entries exist and conform to the expected format.
Forms that pass verification can then be submitted. ARK/RPS allows
PIs to continue to modify submitted proposals
until the deadline, so there is no penalty for submitting the proposal
form early.
The LaTeX, PostScript, and PDF buttons of
ARK/RPS can be used to generate formatted versions of the proposal forms.
Although it is often useful for the PIs to keep formatted copies of the forms
for the record, it is not a required part of the proposal submission process.
The anonymized Scientific/Technical/Management section for a standard and ToO Program must not exceed
4 Letter size (8.5" x 11") pages. The anonymized Scientific/Technical/Management section for a Large and/or Joint Program must not exceed
5 pages. Page limits include figures but not references.
The anonymized Scientific/Technical/Management section can be
generated using the software of the PI's choice, as long
as it is converted to PDF format before submission. However, the font size and margings should meet the
proposal style format requirement described in the ROSES Summary of Solicitation.
Specifically, the text body font size should be no smaller than 15
characters per inch. A 12 point font size is recommended.
Please note that Phase-1 proposals should have a single-column
format. References should be in the [1], [2] format.
Proposals must not contain hyperlinks to additional material other
than references to public information that do not identify the PI,
Co-Is or their institutions; web pages with material specific to the proposal such as target lists or stray light assessments are not allowed.
We suggest that proposers use the LaTeX template or
the Word template for the anonymized Scientific/Technical/Management section. When
using these templates, the user should double-check that the text area
is 6.5" x 9", having at least 1 inch top, botton, right
and left margins on US letter size paper (8.5" x 11").
Content
Proposals should include a description of the scientific
objectives; justify the choice of target(s); show that existing
data (previous X-ray observations or at other wavelengths)
are insufficient to achieve the objectives; justify the choice
of NuSTAR over other existing observatories (preferably
linked to some unique characteristic of NuSTAR);
and demonstrate the feasibility of the proposed observation
and analysis.
Proposals for targets already observed by NuSTAR are
allowed, but must include a justification for an additional
observation, such as a much longer exposure, different pointing
position within an extended object, or different observing window for a
variable object. Observed and/or approved NuSTAR
targets can be found using the HEASARC/Browse numaster table or by using NuSTAR
As-Flown Timeline. A list of approved NuSTAR ToO programs in the NuSTAR, joint NuSTAR/XMM-Newton, joint NuSTAR/Chandra, joint NuSTAR/Swift, and joint NuSTAR/XRISM
GO programs can be found on the NuSTAR SOC page.
Conflicts with Legacy Survey Targets
Observations of targets accepted through the Cycle 12 Call for
Proposals will take precedence over legacy
program observations of those targets. The status of legacy
survey target observations can be found in
HEASARC's numaster table by selecting "EGS", "ELS"
or "GLS" for the obs_type keyword.
The length of the observation should be justified based on the
specific scientific objectives, preferably using simulations or
scaled from prior NuSTAR observations of a similar source.
However, the minimum NuSTAR observing time for a target is
set at 20 ksec.
Proposers should note that NuSTAR's low-inclination (6°), low-Earth orbit allows, on
average, a maximum continuous exposure of ~ 3.2 ks per 5.7 ks satellite orbit for
targets below a declination |Dec| of ~ 65° for targets at high declination, |Dec| > 65°,
the unocculted period may be longer. Unless there is a specific reason why the total
elapsed time of an observation is important, proposers should specify only the net
exposure time required for achievement of the proposed science goals, excluding
observational efficiency factors (Earth occultations and South Atlantic Anomaly
passages) in the observing time calculation; specification of the total elapsed time
requirement will result in the observation being classified as
time-constrained.
Proposals requesting observations of bright sources (predicted instrument count
rate above 100 counts s-1 for both modules using 50% PSF extraction with no
deadtime) with durations > 30 ks are operationally difficult to carry out.
Accordingly, such proposals must provide a sufficiently compelling motivation to
be considered for acceptance. In addition, proposals requesting observations of
bright sources with exposures longer than 75 ks will be considered for
implementation only if the total requested time is distributed in multiple
observations, each with exposure < 75 ks and separated by more than 1 week.
PIs are required to upload a one-page "Expertise and Resources - Not
Anonymized" document PDF through ARK as a separate upload when
submitting the anonymized Scientific/Technical/Management section.
The LaTeX
template or the Word
template is available. (Note that, for NuSTAR proposals, the page
limit for the team expertise document is one page, i.e. further
constrained compared to "no more than three pages" from the general
guidelines document.)
This document provides a list of all team members, their institutional
affiliations, roles, expertise, and contributions to the work. The
document should also discuss any specific resources that are key to
completing the proposed work. If a change of the exclusive-use period from the 6-month default is requested (expected to happen infrequently), a compelling justification e.g., protecting the timely completion of a graduate student's thesis, needs to be added in this document.
This document will be distributed to the review panel after all proposals have been reviewed and rated, only for programs which are in the selectable range. This is to allow the reviewers to assess the team capabilities required to execute a given proposed science investigation.
If there are clear, compelling deficiencies in the expertise required
to see through the goals of the proposal, the panel may decide to flag
the submission accordingly, and provide a detailed justification in
its comments to NASA. This review may not be used to flag "up"
proposals for having strong team qualifications, nor may it be used to
re-evaluate or upgrade proposals.
US PIs whose Phase-1 proposals are assigned a Category A or B rating
by the peer review panel or accepted as a Large Program, i.e.,
Category L, have been invited to submit a Phase-2 (cost) proposal.
US PIs of approved proposals with priority C targets only will be eligible for a
small flat rate grant, awarded through NASA's
Jet Propulsion Laboratory (JPL), if observations are performed. No Phase 2 budget submission is required for these proposals.
If you have any questions concerning NuSTAR or the NuSTAR GO program, visit the Feedback form.