Below is the long term observation plan for the Performance Verification (PV) phase of the XRISM
mission. An alternative (and regularly updated) version of this page can be found on the XRISM JAXA website. The PV phase will commence after checkout and calibration and last for approximately six months. More information about the PV targets can be found here.
PV phase data will be proprietary to the XRISM Science Team for a period of
1 year, after which they will be publicly released and archived.
PV Long term observation plan
Week |
ObsID |
Target |
Remarks |
March 18-24 |
300065010 |
Cyg X-3 |
|
March 25-31 |
300013010 |
3C397 |
|
300040010 |
4U 1624-490 |
|
300013020 |
3C397 |
|
April 01-07 |
300040020 |
4U 1624-490 |
|
300013030 |
3C397 |
|
April 08-14 |
300049010 |
Cyg X-1 |
|
300041010 |
SS433 |
|
April 15-21 |
300039010 |
4U 1916-053 |
|
100009010 |
Cyg X-2 |
|
100008010 |
Cygnus Loop |
|
100008020 |
Cygnus Loop |
|
April 22-28 |
300055010 |
W49B East |
|
April 29 - May 05 |
300056010 |
W49B West |
|
May 06-12 |
300018010 |
M81 |
|
300068010 |
M82 |
|
May 13-19 |
300042020 |
SS Cygni |
|
300047020 |
NGC 4151 |
|
300057010 |
Vela X-1 |
|
May 20-26 |
300016010 |
M87 North-West |
|
300015010 |
M87 Eastern arm |
|
May 27 - June 02 |
300017010 |
M87 South-Western arm |
|
300014010 |
M87 |
|
June 03-09 |
300067010 |
Eta Carinae |
|
300037010 |
2S0921-630 |
|
June 10-16 |
300074010 |
Coma offset |
|
300047030 |
NGC 4151 |
|
June 17-23 |
300021010 |
SN 1987A |
|
300007010 |
Mrk 766 |
|
June 24-30 |
300047040 |
NGC 4151 |
|
300008010 |
T Coronae Borealis |
|
July 01-07 |
300050010 |
NGC 3783 |
|
July 08-14 |
300075020 |
NGC 1365 |
|
July 15-21 |
300073010 |
Coma center |
|
July 22-28 |
300053010 |
Abell 2029 N2 |
|
July 29 - August 04 |
300019010 |
Centaurus A |
|
August 05-11 |
300020010 |
IRAS F05189-252 |
|
August 12-18 |
300002010 |
GX340+00 |
|
August 19-25 |
300005010 |
Kepler SNR |
|
300045020 |
Galactic Center P2 |
|
300046010 |
Galactic Center P3 |
|